In many Price Books there are hundreds even thousands more items.
You can change prices, add and delete items for your needs.
This list is representative of items in this price book (database). It is not all inclusive.
Cost shown for items may not be your cost.
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  0: No Division
Subdivision  0.00: No Subdivision
 0.000000
2007 National Construction Estimator ‑ Commercial
 0.000000
Construction estimating data copyright Craftsman Book Company
Division  1: General Requirements
Subdivision  1.01: Indirect Overhead
 1.010000
*** Indirect Overhead
 1.010005
Rent, office supplies, utilities, equipment, advertising, etc.
M$
20.00
 1.010010
Office salaries and professional fees
M$
60.00
Subdivision  1.02: General Contractor's
 1.020000
*** General Contractor's
 1.020005
indirect overhead General Contractor's
M$
20.00
60.00
Subdivision  1.03: Direct Overhead
 1.030000
*** Direct Overhead
 1.030005
Job superintendent ($4,400 per month)
M$
44.00
 1.030010
Truck and fuel for superintendent ($450 per month)
M$
4.50
 1.030015
Temporary power, light and heat ($250 per month)
M$
2.50
 1.030020
Temporary water ($100 per month)
M$
1.00
 1.030025
Cellular phone ($50 per month)
M$
0.50
 1.030030
Job site toilets ($100 per month)
M$
1.00
 1.030035
Job site office trailer 8' x 30' ($150 per month)
M$
1.50
 1.030040
Storage bin and tool shed 8' x 24' ($80 per month)
M$
0.80
 1.030045
Job site cleanup & debris removal ($300 per month)
M$
3.00
 1.030050
Job signs & first aid equipment ($50 per month)
M$
0.50
Subdivision  1.04: Project Financing
 1.040000
*** Fund control fees
 1.040005
To $200,000 Fund control fees (costs per $1,000 disbursed)
LS
1,000.00
 1.040010
Over $200,000 to $500,000, $1,000 plus Fund control fees (costs per
$1,000 disbursed)
M$
1.50
 1.040015
Over $500,000 to $1,000,000, $1,450 plus Fund control fees (costs per
$1,000 disbursed)
M$
1.00
 1.040020
Over $1,000,000 to $3,000,000, $1,250 plus Fund control fees (costs per
$1,000 disbursed)
M$
0.85
 1.040025
Over $3,000,000 to $5,000,000, $1,150 plus Fund control fees (costs per
$1,000 disbursed)
M$
0.75
 1.040030
Over $5,000,000, $1,000 plus Fund control fees (costs per $1,000
disbursed)
M$
0.55
Subdivision  1.05: Project Scheduling by CPM
 1.050000
*** Project scheduling for wood frame buildings
 1.050005
Simple schedule Wood frame buildings, one or two stories
LS
770.00
 1.050010
Complex schedule Wood frame buildings, one or two stories
LS
1,850.00
 1.050015
*** Project scheduling for tilt‑up concrete buildings
 1.050020
Simple schedule Tilt‑up concrete buildings, 10,000 to 50,000 SF
LS
1,050.00
 1.050025
Complex schedule Tilt‑up concrete buildings, 10,000 to 50,000 SF
LS
1,580.00
 1.050030
*** Project scheduling for mid‑rise buildings
 1.050035
Simple schedule Two to five story buildings (mid rise)
LS
1,900.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  1: General Requirements
Subdivision  1.05: Project Scheduling by CPM
 1.050040
Complex schedule Two to five story buildings (mid rise)
LS
2,680.00
 1.050045
*** Project scheduling for high‑rise buildings
 1.050050
Simple schedule Five to ten story buildings (high rise)
LS
3,090.00
Subdivision  1.06: Sewer Connection Fees
 1.060000
*** Sewer Connection Fees
 1.060005
4" connection and 40' run to main in street Typical charges based on main
up to 11' deep and lateral up to 5' deep
LS
1,680.00
 1.060010
4" pipe runs over 40' to street Typical charges based on main up to 11'
deep and lateral up to 5' deep
LF
38.00
 1.060015
6" connection and 40' run to main in street
LS
2,740.00
 1.060020
6" pipe runs over 40' to street
LF
65.00
 1.060025
4" connection and 15' run to main in alley
LS
1,220.00
 1.060030
6" connection and 15' run to main in alley
LS
1,980.00
 1.060035
Manhole cut‑in
Ea
335.00
Subdivision  1.07: Water Meters
 1.070000
*** Water Meters
 1.070005
1" service, 3/4" meter Water Meters
LS
2,450.00
 1.070010
1" service, 1" meter Water Meters
LS
2,540.00
 1.070015
Add for 1" service per LF over 40' Water Meters
LF
59.00
 1.070020
2" service, 1‑1/2" meter Water Meters
LS
2,850.00
 1.070025
2" service, 2" meter Water Meters
LS
2,950.00
 1.070030
Add for 2" service per LF over 40' Water Meters
LF
63.20
 1.070035
Two 2" service lines and meter manifold Water Meters
LS
4,671.00
 1.070040
Add for two 2" lines per LF over 40' Water Meters
LF
86.70
 1.070045
*** Hydrant meter
 1.070050
Rental per day Water Meters
Day
10.00
Subdivision  1.08: Surveying
 1.080000
*** Surveying
 1.080005
Typical cost Surveying party, 2 or 3 technicians
Day
1,150.00
 1.080010
Higher cost Surveying party, 2 or 3 technicians
Day
1,480.00
 1.080015
Data reduction and drafting Surveying party, 2 or 3 technicians
Hr
70.00
Subdivision  1.09: Surveys
 1.090000
*** Surveys
 1.090005
Residential lot, tract work, 4 corners Surveys
LS
700.00
 1.090010
Residential lot, individual, 4 corners Surveys
LS
1,190.00
 1.090015
Commercial lot, based on 30,000 SF lot Surveys
LS
1,290.00
 1.090020
Over 30,000 SF, add per acre Surveys
Acre
200.00
Subdivision  1.10: Aerial Mapping
 1.100000
*** Aerial Mapping
 1.100005
Back up ground survey including flagging model Aerial Mapping
Ea
3,260.00
 1.100010
Per local flight (Typical "model" is approximately 750' by 1,260' or 25
acres)
Ea
405.00
 1.100015
Vertical photos (2 required per model) (Typical "model" is approximately
750' by 1,260' or 25 acres)
Ea
43.50
 1.100020
Data reduction and drafting, per hour (Typical "model" is approximately
750' by 1,260' or 25 acres)
Hr
60.00
 1.100025
*** Aerial mapping, complete survey
 1.100030
Typical cost per model
Ea
3,390.00
 1.100035
Per model Deduct if ground control is marked on the ground by others
LS
 1.100040
Acre
157.00
Based on 25 acre coverage Typical mapping cost per acre including aerial
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
control, flight and compilation
 1.100045
*** Aerial photos
 1.100050
Black and white Aerial photos, oblique (minimum 4 per job), one 8" x 10"
print
Ea
43.00
Subdivision  1.11: Engineering Fees
 1.110000
*** Engineering Fees
 1.110005
Assistant engineer Registered engineers (calculations, design and
drafting)
Hr
77.00
 1.110010
Senior engineer Registered engineers (calculations, design and drafting)
Hr
131.00
 1.110015
Assistant principal engineer Principal engineers (cost control, project
management, client contact)
Hr
137.00
 1.110020
Senior principal engineer Principal engineers (cost control, project
management, client contact)
Hr
185.00
 1.110025
Job site engineer (specification compliance) Principal engineers (cost
control, project management, client contact)
Hr
77.30
Subdivision  1.12: Estimating Cost
 1.120000
*** Estimating cost for complex facilities
 1.120005
Typical estimator's fee per hour Over $500,000 to $1,000,000
Hr
50.00
Subdivision  1.13: Job Layout
 1.130000
*** Job Layout
 1.130005
Smaller or more complex jobs Job Layout
SF
0.80
 1.130010
Large job, easy work Job Layout
SF
0.50
Subdivision  1.14: General Non‑Distributable Supervision
 1.140000
*** General Non‑Distributable Supervision and Expense
 1.140005
Project manager, typical General Non‑Distributable Supervision and
Expense
Mo
5,690.00
 1.140010
Job superintendent General Non‑Distributable Supervision and Expense
Mo
4,400.00
 1.140015
Factory representative General Non‑Distributable Supervision and
Expense
Day
680.00
 1.140020
Timekeeper General Non‑Distributable Supervision and Expense
Mo
1,830.00
 1.140025
Job site engineer for layout General Non‑Distributable Supervision and
Expense
Mo
3,400.00
 1.140030
Office manager General Non‑Distributable Supervision and Expense
Mo
2,060.00
 1.140035
Office clerk General Non‑Distributable Supervision and Expense
Mo
1,510.00
Subdivision  1.15: Aggregate Testing
 1.150000
*** Aggregate Testing
 1.150005
Add for sample prep Aggregate Testing
Hr
45.00
 1.150010
Abrasion, L.A. Rattler, 100/500 cycles, ASTM C 131 Aggregate Testing
Ea
110.00
 1.150015
Absorption, ASTM C 127, 128 Aggregate Testing
Ea
55.00
 1.150020
Acid solubility Aggregate Testing
Ea
32.00
 1.150025
organic impurities
Ea
45.00
 1.150030
Clay lumps and friable particles, ASTM C 142
Ea
60.00
 1.150035
Coal and lignite, ASTM C 123
Ea
95.00
 1.150040
Material finer than #200 sieve, ASTM C 117
Ea
37.00
 1.150045
Organic impurities, ASTM C 40
Ea
47.00
 1.150050
Percent crushed particles, CAL 205
Ea
63.00
Subdivision  1.16: Asphaltic Concrete Testing
 1.160000
*** Asphaltic concrete core drilling
 1.160005
Per linear inch Asphaltic concrete core drilling, field or laboratory
Ea
5.00
 1.160010
Add for equipment and technician for core drilling Asphaltic concrete core
drilling, field or laboratory
Hr
70.00
 1.160015
Asphaltic core density Asphaltic concrete core drilling, field or laboratory
Ea
25.00
 1.160020
*** Asphaltic concrete testing
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  1: General Requirements
Subdivision  1.16: Asphaltic Concrete Testing
 1.160025
ASTM D 2172 Extraction, percent asphalt, (Method B) excluding ash
correction,
Ea
60.00
 1.160030
ASTM C 136 Gradation on extracted sample (including wash),
Ea
75.00
 1.160035
Maximum density, lab mixed, Marshall, 1559 Gradation on extracted
sample (including wash),
Ea
175.00
 1.160040
Maximum density, premixed, Marshall, 1559 Gradation on extracted
sample (including wash),
Ea
125.00
 1.160045
ASTM 2041 Maximum theoretical unit weight (Rice Gravity),
Ea
75.00
 1.160050
Penetration, ASTM D 5 Maximum theoretical unit weight (Rice Gravity),
Ea
60.00
Subdivision  1.17: Concrete Testing
 1.170000
*** Concrete Testing
 1.170005
Per aggregate size  number 200 wash, organic impurities, weight per
cubic foot
Ea
72.00
 1.170010
Not involving calculations Amend or re‑type existing mix designs
Ea
42.00
 1.170015
ASTM C 42 Compression test, 2", 4", or 6" cores (excludes sample
preparation)
Ea
37.00
 1.170020
ASTM C 39 Compression test, 6" x 12" cylinders, including mold
Ea
13.00
 1.170025
Core cutting in laboratory Compression test, 6" x 12" cylinders, including
mold
Ea
42.00
 1.170030
Cost per cylinder (minimum of 3) Cylinder pickup within 40 miles of
laboratory
Ea
9.00
 1.170035
Flexure test, 6" x 6" beams, ASTM C 78 Cylinder pickup within 40 miles of
laboratory
Ea
53.00
 1.170040
Laboratory trial, concrete batch, ASTM C 192 Cylinder pickup within 40
miles of laboratory
Ea
345.00
 1.170045
ASTM C 157 modified Length change (3 bars, 4 readings, up to 90 days)
LS
240.00
 1.170050
Additional readings, per set of 3 bars Length change (3 bars, 4 readings,
up to 90 days)
LS
37.00
Subdivision  1.18: Masonry and Tile Testing
 1.180000
*** Brick testing
 1.180005
Modulus of rupture (flexure) or compressive strength Brick, ASTM C 67
Ea
27.00
 1.180010
Absorption initial rate, 5 hour or 24 hour Brick, ASTM C 67
Ea
22.00
 1.180015
Boil, 1, 2, or 5 hours Brick, ASTM C 67
Ea
22.00
 1.180020
Efflorescence Brick, ASTM C 67
Ea
27.00
 1.180025
Dimensions, overall, coring, shell and web Brick, ASTM C 67
Ea
22.00
 1.180030
Compression of core Brick, ASTM C 67
Ea
37.00
 1.180035
Cores, shear, 6" and 8" diameter, 2 faces, per core Brick, ASTM C 67
Ea
47.00
 1.180040
Coefficient of friction (slip test) Brick, ASTM C 67
Ea
84.00
 1.180045
*** Concrete block testing
 1.180050
Moisture content as received Concrete block, ASTM C 140
Ea
22.00
Subdivision  1.19: Reinforcement Testing
 1.190000
*** Reinforcement testing, sampling at fabricator's plant
 1.190005
During normal business hours, per sample Sampling at fabricator's plant
(within 40 miles of lab), $50.00 minimum
Ea
18.00
 1.190010
Other than normal business hours, per sample Sampling at fabricator's
plant (within 40 miles of lab), $50.00 minimum
Ea
27.00
 1.190015
Tensile test, mechanically spliced bar Sampling at fabricator's plant (within
40 miles of lab), $50.00 minimum
Ea
100.00
 1.190020
ASTM 615 Tensile test, number 11 bar or smaller,
Ea
26.00
 1.190025
ASTM 615 Tensile test, number 14 bar or smaller,
Ea
58.00
 1.190030
Tensile test, number 18 bar, ASTM 615 Tensile test, number 14 bar or
smaller,
Ea
68.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  1: General Requirements
Subdivision  1.19: Reinforcement Testing
 1.190035
Tensile test, welded number 11 bar or smaller Tensile test, number 14 bar
or smaller,
Ea
37.00
 1.190040
Tensile test, welded number 14 bar Tensile test, number 14 bar or
smaller,
Ea
68.00
 1.190045
Tensile test, welded number 18 bar Tensile test, number 14 bar or
smaller,
Ea
84.00
 1.190050
*** Tensile and elongation test for prestress strands
Subdivision  1.20: Soils and Aggregate Base Testing
 1.200000
*** Soils and Aggregate Base Testing
 1.200005
Bearing ratio (excluding moisture‑density curve) Soils and Aggregate
Base Testing
Ea
110.00
 1.200010
Consolidation test (single point) Soils and Aggregate Base Testing
Ea
75.00
 1.200015
Consolidation test (without rate data) Soils and Aggregate Base Testing
Ea
95.00
 1.200020
*** Direct shear testing of soils
 1.200025
Unconsolidated, undrained Direct shear test
Ea
65.00
 1.200030
Consolidated, undrained Direct shear test
Ea
100.00
 1.200035
Consolidated, drained Direct shear test
Ea
125.00
 1.200040
*** Soils and aggregate testing
 1.200045
Durability index ‑ coarse and fine Direct shear test
Ea
140.00
 1.200050
Expansion index test, UBC 29‑2 Direct shear test
Ea
110.00
Subdivision  1.21: Steel Testing
 1.210000
*** Steel Testing
 1.210005
Charpy impact test, reduced temperature Steel Testing
Ea
26.00
 1.210010
Charpy impact test, room temperature Steel Testing
Ea
13.00
 1.210015
Electric extensometer Steel Testing
Ea
63.00
 1.210020
Hardness tests, Brinell or Rockwell Steel Testing
Ea
22.00
 1.210025
*** Photo micrographs
 1.210030
20x to 2000x Photo micrographs
Ea
22.00
 1.210035
With negative Photo micrographs
Ea
26.00
 1.210040
*** Steel testing
 1.210045
Tensile test, under 100,000 lbs Photo micrographs
Ea
37.00
 1.210050
*** Welder qualification testing
Subdivision  1.22: Construction Photography
 1.220000
*** Job progress photos
 1.220005
Typical cost
LS
550.00
 1.220010
High cost
LS
630.00
 1.220015
*** Periodic survey visits
 1.220020
Minimum two photos, per visit
Ea
355.00
 1.220025
*** Exterior completion photographs
 1.220030
Black and white Exterior completion photographs, two 8" x 10" prints (two
angles)
Ea
550.00
 1.220035
Color Exterior completion photographs, two 8" x 10" prints (two angles)
Ea
550.00
 1.220040
*** Interior completion photographs
 1.220045
Black and white  (minimum three shots)
Ea
630.00
 1.220050
Color  (minimum three shots)
Ea
630.00
Subdivision  1.23: Signs and Markers
 1.230000
*** Signs and Markers
 1.230005
3/4" to 2‑1/2" diameter, 3/4" letters, 7" long Signs and Markers
Ea
1.75
3.44
 1.230010
2‑1/2" to 8" diameter, 1‑1/4" letters, 12" long Signs and Markers
Ea
2.40
3.44
 1.230015
8" to 10" diameter, 2‑1/2" letters, 24" long Signs and Markers
Ea
4.00
3.44
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  1: General Requirements
Subdivision  1.23: Signs and Markers
 1.230020
10" and larger diameter, 3‑1/2" letters, 32" long Signs and Markers
Ea
4.50
4.25
 1.230025
(use $50.00 as minimum material cost) Signs and Markers Flow arrows,
2" wide tape x 108' roll, perforated every 8"
LF
0.52
4.25
 1.230030
*** Barrier tapes
 1.230035
2 mil thick, short‑term or indoor use Barrier tapes, 3" wide x 1,000' long
LF
0.02
0.09
 1.230040
4 mil thick, long‑term or outdoor use Barrier tapes, 3" wide x 1,000' long
LF
0.04
0.09
 1.230045
*** Traffic control signage
 1.230050
6" x 12", reflective
Ea
40.10
13.50
Subdivision  1.24: Temporary Utilities
 1.240000
*** Temporary power pole installation
 1.240005
100 amp meter pole Drop pole for electric service Power pole installation,
wiring, 6 months rent and pickup
Ea
440.00
 1.240010
200 amp meter pole Drop pole for electric service Power pole installation,
wiring, 6 months rent and pickup
Ea
580.00
 1.240015
*** Temporary overhead run to contractor's "T" pole
 1.240020
Single phase, 100 amps Electric drop line and run to contractor's panel
(assuming proper phase, voltage and service are available within 100' of
site)
LS
354.00
 1.240025
Single phase, over 100 to 200 amps Electric drop line and run to
contractor's panel (assuming proper phase, voltage and service are
available within 1
LS
478.00
 1.240030
Three phase, to 200 amps Electric drop line and run to contractor's panel
(assuming proper phase, voltage and service are available within 100' of
sit
LS
550.00
 1.240035
*** Temporary underground run in contractor's trench
 1.240040
Single phase, 100 amps, "USA" wire Electric drop line and run to
contractor's panel (assuming proper phase, voltage and service are
available within 1
LS
510.00
 1.240045
Single phase, 101‑200 amps, "USA" wire Electric drop line and run to
contractor's panel (assuming proper phase, voltage and service are
available with
LS
660.00
 1.240050
Three phase, to 200 amps, "USA" wire Electric drop line and run to
contractor's panel (assuming proper phase, voltage and service are
available within
LS
730.00
Subdivision  1.25: Construction Elevators and Hoists
 1.250000
*** Hoisting towers
 1.250005
Material hoist Hoisting towers to 200', monthly rent
Mo
2,850.00
8,440.00
 1.250010
Personnel hoist Hoisting towers to 200', monthly rent
Mo
6,540.00
8,440.00
 1.250015
*** Tower cranes
 1.250020
5 ton lift at 180' radius, one operator Tower cranes, self‑climbing (electric),
monthly rent
Mo
16,200.00
8,440.00
 1.250025
With two operators Tower cranes, self‑climbing (electric), monthly rent
Mo
16,200.00
16,900.00
 1.250030
7 ton lift at 170' radius, one operator Tower cranes, self‑climbing (electric),
monthly rent
Mo
22,500.00
8,440.00
 1.250035
With two operators Tower cranes, self‑climbing (electric), monthly rent
Mo
22,500.00
16,900.00
 1.250040
*** Mobilize, erect and dismantle self‑climbing tower cranes
 1.250045
Good access Mobilize, erect and dismantle self‑climbing tower cranes
LS
47,600.00
 1.250050
Average access Mobilize, erect and dismantle self‑climbing tower cranes
LS
55,500.00
Subdivision  1.26: Hydraulic Truck Cranes
 1.260000
*** Hydraulic Truck Cranes
 1.260005
12‑1/2 ton Hydraulic Truck Cranes
Hr
162.00
 1.260010
15 ton Hydraulic Truck Cranes
Hr
168.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  1: General Requirements
Subdivision  1.26: Hydraulic Truck Cranes
 1.260015
25 ton Hydraulic Truck Cranes
Hr
178.00
 1.260020
50 ton Hydraulic Truck Cranes
Hr
225.00
 1.260025
70 ton Hydraulic Truck Cranes
Hr
256.00
 1.260030
80 ton Hydraulic Truck Cranes
Hr
277.00
 1.260035
100 ton Hydraulic Truck Cranes
Hr
308.00
 1.260040
125 ton Hydraulic Truck Cranes
Hr
318.00
 1.260045
150 ton Hydraulic Truck Cranes
Hr
350.00
 1.260050
Add for clamshell or breaker ball work Hydraulic Truck Cranes
Hr
40.00
Subdivision  1.27: Conventional Cable Cranes
 1.270000
*** Conventional Cable Cranes
 1.270005
50 tons Conventional Cable Cranes
Hr
240.00
 1.270010
70 tons Conventional Cable Cranes
Hr
274.00
 1.270015
90 tons Conventional Cable Cranes
Hr
308.00
 1.270020
125 tons Conventional Cable Cranes
Hr
342.00
 1.270025
140 tons Conventional Cable Cranes
Hr
334.00
Subdivision  1.28: Air equipment rental
 1.280000
*** Air compressor rental
 1.280005
Rental for Day 16 CFM, shop type, electric Air compressors,
wheel‑mounted
Day
45.00
 1.280010
Rental for Week 16 CFM, shop type, electric Air compressors,
wheel‑mounted
Week
136.00
 1.280015
Rental for Month 16 CFM, shop type, electric Air compressors,
wheel‑mounted
Month
408.00
 1.280020
Rental for Day 30 CFM, shop type, electric Air compressors,
wheel‑mounted
Day
63.00
 1.280025
Rental for Week 30 CFM, shop type, electric Air compressors,
wheel‑mounted
Week
187.00
 1.280030
Rental for Month 30 CFM, shop type, electric Air compressors,
wheel‑mounted
Month
562.00
 1.280035
Rental for Day 80 CFM, shop type, electric Air compressors,
wheel‑mounted
Day
73.00
 1.280040
Rental for Week 80 CFM, shop type, electric Air compressors,
wheel‑mounted
Week
221.00
 1.280045
Rental for Month 80 CFM, shop type, electric Air compressors,
wheel‑mounted
Month
663.00
 1.280050
Rental for Day 100 CFM, gasoline unit Air compressors, wheel‑mounted
Day
91.00
Subdivision  1.29: Compaction equipment rental
 1.290000
*** Compaction equipment rental
 1.290005
Rental for Day Vibro plate, 300 lb, 24" plate width, gas Compaction
equipment rental
Day
80.00
 1.290010
Rental for Week Vibro plate, 300 lb, 24" plate width, gas Compaction
equipment rental
Week
250.00
 1.290015
Rental for Month Vibro plate, 300 lb, 24" plate width, gas Compaction
equipment rental
Month
700.00
 1.290020
Rental for Day Vibro plate, 600 lb, 32" plate width, gas Compaction
equipment rental
Day
135.00
 1.290025
Rental for Week Vibro plate, 600 lb, 32" plate width, gas Compaction
equipment rental
Week
415.00
 1.290030
Rental for Month Vibro plate, 600 lb, 32" plate width, gas Compaction
equipment rental
Month
1,160.00
 1.290035
Rental for Day Rammer, 60 CPM, 200 lb, gas powered Compaction
equipment rental
Day
70.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  1: General Requirements
Subdivision  1.29: Compaction equipment rental
 1.290040
Rental for Week Rammer, 60 CPM, 200 lb, gas powered Compaction
equipment rental
Week
215.00
 1.290045
Rental for Month Rammer, 60 CPM, 200 lb, gas powered Compaction
equipment rental
Month
600.00
 1.290050
*** Roller rental, two axle steel drum
Subdivision  1.30: Concrete equipment rental
 1.300000
*** Concrete equipment rental
 1.300005
Rental for Day Buggies, push type, 7 CF Concrete equipment rental
Day
44.00
 1.300010
Rental for Week Buggies, push type, 7 CF Concrete equipment rental
Week
150.00
 1.300015
Rental for Month Buggies, push type, 7 CF Concrete equipment rental
Month
400.00
 1.300020
Rental for Day Buggies, walking type, 12 CF Concrete equipment rental
Day
65.00
 1.300025
Rental for Week Buggies, walking type, 12 CF Concrete equipment rental
Week
190.00
 1.300030
Rental for Month Buggies, walking type, 12 CF Concrete equipment rental
Month
535.00
 1.300035
Rental for Day Buggies, riding type, 14 CF Concrete equipment rental
Day
90.00
 1.300040
Rental for Week Buggies, riding type, 14 CF Concrete equipment rental
Week
275.00
 1.300045
Rental for Month Buggies, riding type, 14 CF Concrete equipment rental
Month
710.00
 1.300050
Rental for Day Buggies, riding type, 18 CF Concrete equipment rental
Day
105.00
Subdivision  1.31: Crane rental
 1.310000
*** Crane rental
 1.310005
Rental for Month 45 ton Cable controlled crawler‑mounted lifting cranes,
diesel
Month
6,000.00
 1.310010
Rental for Week 60 ton Cable controlled crawler‑mounted lifting cranes,
diesel
Week
2,880.00
 1.310015
Rental for Month 60 ton Cable controlled crawler‑mounted lifting cranes,
diesel
Month
8,600.00
 1.310020
Rental for Day 100 ton (125 ton) Cable controlled crawler‑mounted lifting
cranes, diesel
Day
1,200.00
 1.310025
Rental for Week 100 ton (125 ton) Cable controlled crawler‑mounted
lifting cranes, diesel
Week
4,840.00
 1.310030
Rental for Month 100 ton (125 ton) Cable controlled crawler‑mounted
lifting cranes, diesel
Month
13,650.00
 1.310035
Rental for Day 150 ton Cable controlled crawler‑mounted lifting cranes,
diesel
Day
2,000.00
 1.310040
Rental for Week 150 ton Cable controlled crawler‑mounted lifting cranes,
diesel
Week
5,900.00
 1.310045
Rental for Month 150 ton Cable controlled crawler‑mounted lifting cranes,
diesel
Month
20,000.00
 1.310050
*** Cable controlled truck mounted lifting crane rental
Subdivision  1.32: Clamshell, dragline, and pile driver
 1.320000
*** Clamshell bucket rental
 1.320005
Rental for Week Rehandling type, 1 CY Clamshell, dragline, and pile
driver attachments Clamshell buckets
Week
320.00
 1.320010
Rental for Month Rehandling type, 1 CY Clamshell, dragline, and pile
driver attachments Clamshell buckets
Month
950.00
 1.320015
Rental for Day General purpose, 2 CY Clamshell, dragline, and pile driver
attachments Clamshell buckets
Day
80.00
 1.320020
Rental for Week General purpose, 2 CY Clamshell, dragline, and pile
driver attachments Clamshell buckets
Week
510.00
 1.320025
Rental for Month General purpose, 2 CY Clamshell, dragline, and pile
driver attachments Clamshell buckets
Month
1,370.00
 1.320030
*** Dragline bucket rental
 1.320035
Day
44.00
Rental for Day 1 CY bucket Clamshell, dragline, and pile driver
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
attachments Dragline buckets
 1.320040
Rental for Week 1 CY bucket Clamshell, dragline, and pile driver
attachments Dragline buckets
Week
110.00
 1.320045
Rental for Month 1 CY bucket Clamshell, dragline, and pile driver
attachments Dragline buckets
Month
310.00
 1.320050
Rental for Day 2 CY bucket Clamshell, dragline, and pile driver
attachments Dragline buckets
Day
83.00
Subdivision  1.33: Excavation equipment rental
 1.330000
*** Crawler mounted backhoe rental
 1.330005
Rental for Day 3/8 CY backhoe Backhoe/loaders, crawler mounted, diesel
Day
300.00
 1.330010
Rental for Week 3/8 CY backhoe Backhoe/loaders, crawler mounted,
diesel
Week
995.00
 1.330015
Rental for Month 3/8 CY backhoe Backhoe/loaders, crawler mounted,
diesel
Month
2,920.00
 1.330020
Rental for Day 3/4 CY backhoe Backhoe/loaders, crawler mounted, diesel
Day
390.00
 1.330025
Rental for Week 3/4 CY backhoe Backhoe/loaders, crawler mounted,
diesel
Week
1,140.00
 1.330030
Rental for Month 3/4 CY backhoe Backhoe/loaders, crawler mounted,
diesel
Month
3,260.00
 1.330035
Rental for Day 1‑1/2 CY backhoe Backhoe/loaders, crawler mounted,
diesel
Day
435.00
 1.330040
Rental for Week 1‑1/2 CY backhoe Backhoe/loaders, crawler mounted,
diesel
Week
1,310.00
 1.330045
Rental for Month 1‑1/2 CY backhoe Backhoe/loaders, crawler mounted,
diesel
Month
3,860.00
 1.330050
Rental for Day 2 CY backhoe Backhoe/loaders, crawler mounted, diesel
Day
630.00
Subdivision  1.34: Forklift rental
 1.340000
*** Rough terrain forklift rental
 1.340005
Rental for Day 4,000 lb capacity Rough terrain, towable, gas powered
Day
250.00
 1.340010
Rental for Week 4,000 lb capacity Rough terrain, towable, gas powered
Week
700.00
 1.340015
Rental for Month 4,000 lb capacity Rough terrain, towable, gas powered
Month
1,800.00
 1.340020
Rental for Day 8,000 lb capacity Rough terrain, towable, gas powered
Day
225.00
 1.340025
Rental for Week 8,000 lb capacity Rough terrain, towable, gas powered
Week
670.00
 1.340030
Rental for Month 8,000 lb capacity Rough terrain, towable, gas powered
Month
1,920.00
 1.340035
*** Extension boom rental
 1.340040
Rental for Day 4,000 lb, 30' lift Extension boom, 2 wheel steering
Day
240.00
 1.340045
Rental for Week 4,000 lb, 30' lift Extension boom, 2 wheel steering
Week
700.00
 1.340050
Rental for Month 4,000 lb, 30' lift Extension boom, 2 wheel steering
Month
2,040.00
Subdivision  1.35: Aerial platform rental
 1.350000
*** Rolling scissor lift rental
 1.350005
Rental for Day 30' high
Day
70.00
 1.350010
Rental for Week 30' high
Week
195.00
 1.350015
Rental for Month 30' high
Month
550.00
 1.350020
Rental for Day 40' high
Day
140.00
 1.350025
Rental for Week 40' high
Week
380.00
 1.350030
Rental for Month 40' high
Month
980.00
 1.350035
Rental for Day 50' high
Day
204.00
 1.350040
Rental for Week 50' high
Week
555.00
 1.350045
Rental for Month 50' high
Month
1,510.00
 1.350050
*** Electric rolling scissor lift rental
Subdivision  1.36: Pump rental
 1.360000
*** Submersible pump rental
 1.360005
Rental for Day 1‑1/2" to 2", electric Submersible pump rental
Day
34.00
 1.360010
Rental for Week 1‑1/2" to 2", electric Submersible pump rental
Week
105.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  1: General Requirements
Subdivision  1.36: Pump rental
 1.360015
Rental for Month 1‑1/2" to 2", electric Submersible pump rental
Month
298.00
 1.360020
Rental for Day 3" to 4", electric Submersible pump rental
Day
75.00
 1.360025
Rental for Week 3" to 4", electric Submersible pump rental
Week
250.00
 1.360030
Rental for Month 3" to 4", electric Submersible pump rental
Month
680.00
 1.360035
Rental for Day All diameters, hydraulic Submersible pump rental
Day
245.00
 1.360040
Rental for Week All diameters, hydraulic Submersible pump rental
Week
765.00
 1.360045
Rental for Month All diameters, hydraulic Submersible pump rental
Month
2,300.00
 1.360050
*** Trash pump rental
Subdivision  1.37: Sandblasting equipment rental
 1.370000
*** Compressor and hopper rental
 1.370005
Rental for Day To 250 PSI Compressor and hopper
Day
70.00
 1.370010
Rental for Week To 250 PSI Compressor and hopper
Week
220.00
 1.370015
Rental for Month To 250 PSI Compressor and hopper
Month
570.00
 1.370020
Rental for Day Over 250 to 300 PSI Compressor and hopper
Day
80.00
 1.370025
Rental for Week Over 250 to 300 PSI Compressor and hopper
Week
250.00
 1.370030
Rental for Month Over 250 to 300 PSI Compressor and hopper
Month
735.00
 1.370035
Rental for Day Over 600 PSI to 1,000 PSI Compressor and hopper
Day
130.00
 1.370040
Rental for Week Over 600 PSI to 1,000 PSI Compressor and hopper
Week
415.00
 1.370045
Rental for Month Over 600 PSI to 1,000 PSI Compressor and hopper
Month
1,180.00
 1.370050
Rental for Day 3/4" sandblast hose or air hose Sandblasting accessories
Hoses, 50', coupled
Day
8.00
Subdivision  1.38: Roadway equipment rental
 1.380000
*** Roadway equipment rental
 1.380005
Rental for Day Boom mounted pavement breaker, hydraulic 1,500 lb
Roadway equipment rental
Day
355.00
 1.380010
Rental for Week Boom mounted pavement breaker, hydraulic 1,500 lb
Roadway equipment rental
Week
1,150.00
 1.380015
Rental for Month Boom mounted pavement breaker, hydraulic 1,500 lb
Roadway equipment rental
Month
3,200.00
 1.380020
Rental for Day pneumatic, 1,000 lb Paving breaker, backhoe mount,
Day
270.00
 1.380025
Rental for Week pneumatic, 1,000 lb Paving breaker, backhoe mount,
Week
800.00
 1.380030
Rental for Month pneumatic, 1,000 lb Paving breaker, backhoe mount,
Month
2,270.00
 1.380035
Rental for Day Asphalt curbing machine Paving breaker, backhoe mount,
Day
88.00
 1.380040
Rental for Week Asphalt curbing machine Paving breaker, backhoe
mount,
Week
265.00
 1.380045
Rental for Month Asphalt curbing machine Paving breaker, backhoe
mount,
Month
800.00
 1.380050
Rental for Day Paving machine, diesel, 10' width, self propelled Paving
breaker, backhoe mount,
Day
1,470.00
Subdivision  1.39: Traffic control equipment rental
 1.390000
*** Traffic control equipment rental
 1.390005
Rental for Day Arrow board ‑ 25 lights Traffic control equipment rental
Day
65.00
 1.390010
Rental for Week Arrow board ‑ 25 lights Traffic control equipment rental
Week
200.00
 1.390015
Rental for Month Arrow board ‑ 25 lights Traffic control equipment rental
Month
550.00
 1.390020
Rental for Day Barricades Traffic control equipment rental
Day
6.00
 1.390025
Rental for Week Barricades Traffic control equipment rental
Week
15.00
 1.390030
Rental for Month Barricades Traffic control equipment rental
Month
40.00
 1.390035
Rental for Day Barricades with flashers Traffic control equipment rental
Day
6.00
 1.390040
Rental for Week Barricades with flashers Traffic control equipment rental
Week
18.00
 1.390045
Rental for Month Barricades with flashers Traffic control equipment rental
Month
50.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  1: General Requirements
Subdivision  1.39: Traffic control equipment rental
 1.390050
Rental for Day Delineators Traffic control equipment rental
Day
4.00
Subdivision  1.40: Drill rental
 1.400000
*** Drill rental
 1.400005
Rental for Day 1/2" cordless drill, 18 volt Drill rental
Day
11.00
 1.400010
Rental for Week 1/2" cordless drill, 18 volt Drill rental
Week
42.00
 1.400015
Rental for Month 1/2" cordless drill, 18 volt Drill rental
Month
125.00
 1.400020
Rental for Day 3/8" or 1/2", electric drill Drill rental
Day
11.00
 1.400025
Rental for Week 3/8" or 1/2", electric drill Drill rental
Week
42.00
 1.400030
Rental for Month 3/8" or 1/2", electric drill Drill rental
Month
125.00
 1.400035
Rental for Day 3/4" electric drill Drill rental
Day
26.00
 1.400040
Rental for Week 3/4" electric drill Drill rental
Week
105.00
 1.400045
Rental for Month 3/4" electric drill Drill rental
Month
315.00
 1.400050
Rental for Day 1/2" right angle electric drill Drill rental
Day
28.00
Subdivision  1.41: Electric generator rental
 1.410000
*** Electric generator rental
 1.410005
Rental for Day 2.5 kw, gasoline Electric generator rental
Day
40.00
 1.410010
Rental for Week 2.5 kw, gasoline Electric generator rental
Week
170.00
 1.410015
Rental for Month 2.5 kw, gasoline Electric generator rental
Month
500.00
 1.410020
Rental for Day 5 kw, gasoline Electric generator rental
Day
45.00
 1.410025
Rental for Week 5 kw, gasoline Electric generator rental
Week
235.00
 1.410030
Rental for Month 5 kw, gasoline Electric generator rental
Month
700.00
 1.410035
Rental for Day 15 kw, diesel Electric generator rental
Day
115.00
 1.410040
Rental for Week 15 kw, diesel Electric generator rental
Week
320.00
 1.410045
Rental for Month 15 kw, diesel Electric generator rental
Month
900.00
 1.410050
Rental for Day 60 kw, diesel Electric generator rental
Day
260.00
Subdivision  1.42: Floor equipment rental
 1.420000
*** Floor equipment rental
 1.420005
Rental for Day Carpet blower Floor equipment rental
Day
22.00
 1.420010
Rental for Week Carpet blower Floor equipment rental
Week
85.00
 1.420015
Rental for Month Carpet blower Floor equipment rental
Month
250.00
 1.420020
Rental for Day Carpet cleaner Floor equipment rental
Day
25.00
 1.420025
Rental for Week Carpet cleaner Floor equipment rental
Week
90.00
 1.420030
Rental for Month Carpet cleaner Floor equipment rental
Month
270.00
 1.420035
Rental for Day Carpet kicker Floor equipment rental
Day
15.00
 1.420040
Rental for Week Carpet kicker Floor equipment rental
Week
60.00
 1.420045
Rental for Month Carpet kicker Floor equipment rental
Month
175.00
 1.420050
Rental for Day Carpet power stretcher
Day
28.00
Subdivision  1.43: Hammer rental
 1.430000
*** Hammer rental
 1.430005
Rental for Day Electric brute breaker Hammer rental
Day
60.00
 1.430010
Rental for Week Electric brute breaker Hammer rental
Week
225.00
 1.430015
Rental for Month Electric brute breaker Hammer rental
Month
675.00
 1.430020
Rental for Day Gas breaker Hammer rental
Day
63.00
 1.430025
Rental for Week Gas breaker Hammer rental
Week
252.00
 1.430030
Rental for Month Gas breaker Hammer rental
Month
756.00
 1.430035
Rental for Day Demolition hammer, electric Hammer rental
Day
50.00
 1.430040
Rental for Week Demolition hammer, electric Hammer rental
Week
190.00
 1.430045
Rental for Month Demolition hammer, electric Hammer rental
Month
575.00
 1.430050
Rental for Day Roto hammer, 7/8", electric Hammer rental
Day
50.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  1: General Requirements
Subdivision  1.44: Heater rental
 1.440000
*** Heater rental
 1.440005
Rental for Day Kerosene heater, to 200 MBtu Heater rental
Day
40.00
 1.440010
Rental for Week Kerosene heater, to 200 MBtu Heater rental
Week
125.00
 1.440015
Rental for Month Kerosene heater, to 200 MBtu Heater rental
Month
360.00
 1.440020
Rental for Day Kerosene heater, over 200 to 300 MBtu Heater rental
Day
40.00
 1.440025
Rental for Week Kerosene heater, over 200 to 300 MBtu Heater rental
Week
135.00
 1.440030
Rental for Month Kerosene heater, over 200 to 300 MBtu Heater rental
Month
350.00
 1.440035
Rental for Day Kerosene heater,over 500 to 1,000 MBtu Heater rental
Day
75.00
 1.440040
Rental for Week Kerosene heater,over 500 to 1,000 MBtu Heater rental
Week
230.00
 1.440045
Rental for Month Kerosene heater,over 500 to 1,000 MBtu Heater rental
Month
640.00
 1.440050
Rental for Day Salamanders, LP gas (no powered fan) Heater rental
Day
40.00
Subdivision  1.45: Ladder rental
 1.450000
*** Ladder rental
 1.450005
Rental for Day Step ladder, 6' or 8' Ladder rental
Day
15.00
 1.450010
Rental for Week Step ladder, 6' or 8' Ladder rental
Week
55.00
 1.450015
Rental for Month Step ladder, 6' or 8' Ladder rental
Month
160.00
 1.450020
Rental for Day Step ladder, 10' or 14' Ladder rental
Day
20.00
 1.450025
Rental for Week Step ladder, 10' or 14' Ladder rental
Week
75.00
 1.450030
Rental for Month Step ladder, 10' or 14' Ladder rental
Month
220.00
 1.450035
Rental for Day Extension ladder, 24' Ladder rental
Day
32.00
 1.450040
Rental for Week Extension ladder, 24' Ladder rental
Week
125.00
 1.450045
Rental for Month Extension ladder, 24' Ladder rental
Month
365.00
 1.450050
Rental for Day Extension ladder, 28' or 32' Ladder rental
Day
33.00
Subdivision  1.46: Landscape equipment rental
 1.460000
*** Landscape equipment rental
 1.460005
Rental for Day Aerator, gas Landscape equipment rental
Day
55.00
 1.460010
Rental for Week Aerator, gas Landscape equipment rental
Week
189.00
 1.460015
Rental for Month Aerator, gas Landscape equipment rental
Month
567.00
 1.460020
Rental for Day Air broom backpack, gas Landscape equipment rental
Day
32.00
 1.460025
Rental for Week Air broom backpack, gas Landscape equipment rental
Week
126.00
 1.460030
Rental for Month Air broom backpack, gas Landscape equipment rental
Month
378.00
 1.460035
Rental for Day Auger, 2 man (gas) Landscape equipment rental
Day
60.00
 1.460040
Rental for Week Auger, 2 man (gas) Landscape equipment rental
Week
240.00
 1.460045
Rental for Month Auger, 2 man (gas) Landscape equipment rental
Month
660.00
 1.460050
Rental for Day 3" chipper, gas Landscape equipment rental
Day
90.00
Subdivision  1.47: Level rental
 1.470000
*** Level rental
 1.470005
Rental for Day Laser level, small Level rental
Day
44.00
 1.470010
Rental for Week Laser level, small Level rental
Week
158.00
 1.470015
Rental for Month Laser level, small Level rental
Month
504.00
 1.470020
Rental for Day Level kit Level rental
Day
60.00
 1.470025
Rental for Week Level kit Level rental
Week
205.00
 1.470030
Rental for Month Level kit Level rental
Month
605.00
 1.470035
Rental for Day Transit level kit Level rental
Day
41.00
 1.470040
Rental for Week Transit level kit Level rental
Week
170.00
 1.470045
Rental for Month Transit level kit Level rental
Month
500.00
Subdivision  1.48: Light tower rental
 1.480000
*** Light tower rental
 1.480005
Rental for Day Floodlight, 1,000 watt, on stand Light tower rental
Day
35.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  1: General Requirements
Subdivision  1.48: Light tower rental
 1.480010
Rental for Week Floodlight, 1,000 watt, on stand Light tower rental
Week
115.00
 1.480015
Rental for Month Floodlight, 1,000 watt, on stand Light tower rental
Month
350.00
 1.480020
Rental for Day To 7,000 watt trailer mounted light set, gas Light tower
rental
Day
80.00
 1.480025
Rental for Week To 7,000 watt trailer mounted light set, gas Light tower
rental
Week
250.00
 1.480030
Rental for Month To 7,000 watt trailer mounted light set, gas Light tower
rental
Month
675.00
 1.480035
Rental for Day Over 7,000 watt trailer mounted light set, gas Light tower
rental
Day
105.00
 1.480040
Rental for Week Over 7,000 watt trailer mounted light set, gas Light tower
rental
Week
320.00
 1.480045
Rental for Month Over 7,000 watt trailer mounted light set, gas Light tower
rental
Month
900.00
 1.480050
Rental for Day Extension cord, 50' Light tower rental
Day
8.00
Subdivision  1.49: Nailer and stapler rental
 1.490000
*** Nailer and stapler rental
 1.490005
Rental for Day Drywall screwdriver Nailer and stapler rental
Day
15.00
 1.490010
Rental for Week Drywall screwdriver Nailer and stapler rental
Week
60.00
 1.490015
Rental for Month Drywall screwdriver Nailer and stapler rental
Month
170.00
 1.490020
Rental for Day Finish nailer, pneumatic or cordless Nailer and stapler
rental
Day
32.00
 1.490025
Rental for Week Finish nailer, pneumatic or cordless Nailer and stapler
rental
Week
125.00
 1.490030
Rental for Month Finish nailer, pneumatic or cordless Nailer and stapler
rental
Month
365.00
 1.490035
Rental for Day Floor stapler, pneumatic Nailer and stapler rental
Day
35.00
 1.490040
Rental for Week Floor stapler, pneumatic Nailer and stapler rental
Week
130.00
 1.490045
Rental for Month Floor stapler, pneumatic Nailer and stapler rental
Month
390.00
 1.490050
Rental for Day Framing nailer, cordless Nailer and stapler rental
Day
32.00
Subdivision  1.50: Painting equipment rental
 1.500000
*** Painting equipment rental
 1.500005
Rental for Day Airless paint sprayer ‑ large Painting equipment rental
Day
75.00
 1.500010
Rental for Week Airless paint sprayer ‑ large Painting equipment rental
Week
265.00
 1.500015
Rental for Month Airless paint sprayer ‑ large Painting equipment rental
Month
790.00
 1.500020
Rental for Day Heat gun blower Painting equipment rental
Day
10.00
 1.500025
Rental for Week Heat gun blower Painting equipment rental
Week
34.00
 1.500030
Rental for Month Heat gun blower Painting equipment rental
Month
101.00
 1.500035
Rental for Day Mud mixing paddle Painting equipment rental
Day
9.00
 1.500040
Rental for Week Mud mixing paddle Painting equipment rental
Week
34.00
 1.500045
Rental for Month Mud mixing paddle Painting equipment rental
Month
100.00
 1.500050
Rental for Day Pressure washer ‑ cold, 1,500 PSI Painting equipment
rental
Day
65.00
Subdivision  1.51: Plumbing and piping equipment rental
 1.510000
*** Plumbing and piping equipment rental
 1.510005
Rental for Day Basin wrench, 3/8" to 1‑1/4 Plumbing and piping
equipment rental
Day
12.00
 1.510010
Rental for Week Basin wrench, 3/8" to 1‑1/4 Plumbing and piping
equipment rental
Week
35.00
 1.510015
Rental for Month Basin wrench, 3/8" to 1‑1/4 Plumbing and piping
equipment rental
Month
100.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  1: General Requirements
Subdivision  1.51: Plumbing and piping equipment rental
 1.510020
Rental for Day Chain wrench Plumbing and piping equipment rental
Day
9.00
 1.510025
Rental for Week Chain wrench Plumbing and piping equipment rental
Week
34.00
 1.510030
Rental for Month Chain wrench Plumbing and piping equipment rental
Month
101.00
 1.510035
Rental for Day Conduit & pipe cutter Plumbing and piping equipment
rental
Day
15.00
 1.510040
Rental for Week Conduit & pipe cutter Plumbing and piping equipment
rental
Week
50.00
 1.510045
Rental for Month Conduit & pipe cutter Plumbing and piping equipment
rental
Month
150.00
 1.510050
Rental for Day Drain cleaner, corded drill, 3/8 Plumbing and piping
equipment rental
Day
39.00
Subdivision  1.52: Sanding equipment rental
 1.520000
*** Sanding equipment rental
 1.520005
Rental for Day Belt sander, 3" x 21 Sanding equipment rental
Day
17.00
 1.520010
Rental for Week Belt sander, 3" x 21 Sanding equipment rental
Week
63.00
 1.520015
Rental for Month Belt sander, 3" x 21 Sanding equipment rental
Month
189.00
 1.520020
Rental for Day Belt sander, 4" x 24 Sanding equipment rental
Day
25.00
 1.520025
Rental for Week Belt sander, 4" x 24 Sanding equipment rental
Week
100.00
 1.520030
Rental for Month Belt sander, 4" x 24 Sanding equipment rental
Month
290.00
 1.520035
Rental for Day Drywall sander and vacuum Sanding equipment rental
Day
50.00
 1.520040
Rental for Week Drywall sander and vacuum Sanding equipment rental
Week
190.00
 1.520045
Rental for Month Drywall sander and vacuum Sanding equipment rental
Month
560.00
 1.520050
Rental for Day Floor sander, drum type Sanding equipment rental
Day
45.00
Subdivision  1.53: Saw rental
 1.530000
*** Saw rental
 1.530005
Rental for Day Band saw, electric Saw rental
Day
30.00
 1.530010
Rental for Week Band saw, electric Saw rental
Week
120.00
 1.530015
Rental for Month Band saw, electric Saw rental
Month
360.00
 1.530020
Rental for Day Bolt cutters, 24 Saw rental
Day
11.00
 1.530025
Rental for Week Bolt cutters, 24 Saw rental
Week
29.00
 1.530030
Rental for Month Bolt cutters, 24 Saw rental
Month
84.00
 1.530035
Rental for Day Bolt cutters, 36 Saw rental
Day
10.00
 1.530040
Rental for Week Bolt cutters, 36 Saw rental
Week
32.00
 1.530045
Rental for Month Bolt cutters, 36 Saw rental
Month
96.00
 1.530050
Rental for Day Chain saws, 18", gasoline Saw rental
Day
50.00
Subdivision  1.54: Scaffolding rental
 1.540000
*** Scaffolding rental
 1.540005
Rental for Day 5' high, with casters Scaffolding rental
Day
32.00
 1.540010
Rental for Week 5' high, with casters Scaffolding rental
Week
32.00
 1.540015
Rental for Month 5' high, with casters Scaffolding rental
Month
95.00
 1.540020
Rental for Day 10' high, with casters Scaffolding rental
Day
45.00
 1.540025
Rental for Week 10' high, with casters Scaffolding rental
Week
45.00
 1.540030
Rental for Month 10' high, with casters Scaffolding rental
Month
135.00
 1.540035
Rental for Day 15' high, with casters Scaffolding rental
Day
65.00
 1.540040
Rental for Week 15' high, with casters Scaffolding rental
Week
65.00
 1.540045
Rental for Month 15' high, with casters Scaffolding rental
Month
190.00
 1.540050
Rental for Day 5' high, with leg jacks Scaffolding rental
Day
28.00
Subdivision  1.55: Welding equipment rental
 1.550000
*** Welding equipment rental
 1.550005
Rental for Day To 200 amp Welding equipment rental
Day
60.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  1: General Requirements
Subdivision  1.55: Welding equipment rental
 1.550010
Rental for Week To 200 amp Welding equipment rental
Week
200.00
 1.550015
Rental for Month To 200 amp Welding equipment rental
Month
550.00
 1.550020
Rental for Day 201 to 300 amp Welding equipment rental
Day
90.00
 1.550025
Rental for Week 201 to 300 amp Welding equipment rental
Week
270.00
 1.550030
Rental for Month 201 to 300 amp Welding equipment rental
Month
750.00
Subdivision  1.56: Miscellaneous equipment rental
 1.560000
*** Miscellaneous equipment rental
 1.560005
Rental for Day Aluminum break, 10' Miscellaneous equipment rental
Day
53.00
 1.560010
Rental for Week Aluminum break, 10' Miscellaneous equipment rental
Week
210.00
 1.560015
Rental for Month Aluminum break, 10' Miscellaneous equipment rental
Month
630.00
 1.560020
Rental for Day Appliance dolly Miscellaneous equipment rental
Day
14.00
 1.560025
Rental for Week Appliance dolly Miscellaneous equipment rental
Week
50.00
 1.560030
Rental for Month Appliance dolly Miscellaneous equipment rental
Month
150.00
 1.560035
Rental for Day Chain hoist, 1 ton, 20' lift Miscellaneous equipment rental
Day
21.00
 1.560040
Rental for Week Chain hoist, 1 ton, 20' lift Miscellaneous equipment rental
Week
84.00
 1.560045
Rental for Month Chain hoist, 1 ton, 20' lift Miscellaneous equipment
rental
Month
252.00
 1.560050
Rental for Day Chain hoist, 5 ton, 20' lift Miscellaneous equipment rental
Day
34.00
Subdivision  1.57: Scaffolding Rental
 1.570000
*** Scaffolding Rental
 1.570005
With plank on scaffold only Costs are per square foot of building wall
covered, per month
SF
0.96
 1.570010
With plank on side brackets and scaffold Costs are per square foot of
building wall covered, per month
SF
1.20
 1.570015
*** Add for erection and dismantling
 1.570020
With plank on scaffold only Costs are per square foot of building wall
covered, per month Add for erection and dismantling, level ground, truck
access
SF
0.29
 1.570025
With planks on side brackets and scaffold Costs are per square foot of
building wall covered, per month Add for erection and dismantling, level
ground
SF
0.44
 1.570030
*** Caster‑mounted scaffolding rental
 1.570035
6' high Costs are per square foot of building wall covered, per month
Mo
120.00
 1.570040
7' high Costs are per square foot of building wall covered, per month
Mo
130.00
 1.570045
10' high Costs are per square foot of building wall covered, per month
Mo
140.00
 1.570050
13' high Costs are per square foot of building wall covered, per month
Mo
150.00
Subdivision  1.58: Heavy Duty Shoring
 1.580000
*** Heavy Duty Shoring
 1.580005
Rental per frame per month Heavy Duty Shoring Frames (any size),
including braces and assembly hardware
Mo
11.00
 1.580010
*** Screw jacks
 1.580015
Rental per jack per month Screw jacks (four required per frame with base
plate or "U" head)
Mo
4.75
 1.580020
Add for erecting each frame Screw jacks (four required per frame with
base plate or "U" head)
Ea
8.88
 1.580025
Add for dismantling each frame Screw jacks (four required per frame with
base plate or "U" head)
Ea
7.14
Subdivision  1.59: Temporary Structures
 1.590000
*** Temporary Structures
 1.590005
16' x  8' x  7' high (108 SF) Temporary Structures
Mo
155.00
 1.590010
20' x  8' x  7' high (160 SF) Temporary Structures
Mo
165.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  1: General Requirements
Subdivision  1.59: Temporary Structures
 1.590015
24' x  8' x  7' high (192 SF) Temporary Structures
Mo
175.00
 1.590020
28' x  8' x  7' high (240 SF) Temporary Structures
Mo
185.00
 1.590025
28' x 10' x 10' high (360 SF) Temporary Structures
Mo
226.00
 1.590030
40' x 10' x 10' high (440 SF) Temporary Structures
Mo
257.00
 1.590035
48' x 10' x 10' high (500 SF) Temporary Structures
Mo
288.00
 1.590040
40' x 12' x 10' high (552 SF) Temporary Structures
Mo
288.00
 1.590045
60' x 12' x 10' high (720 SF) Temporary Structures
Mo
370.00
 1.590050
60' x 14' x 10' high (840 SF) Temporary Structures
Mo
380.00
Subdivision  1.60: Temporary Enclosures
 1.600000
*** Temporary chain link fence
 1.600005
Less than 250 feet Chain link fence, 6' high
LF
1.75
 1.600010
250 to 500 feet Chain link fence, 6' high
LF
1.70
 1.600015
501 to 750 feet Chain link fence, 6' high
LF
1.60
 1.600020
751 to 1,000 feet Chain link fence, 6' high
LF
1.35
 1.600025
Over 1,000 feet Chain link fence, 6' high
LF
1.18
 1.600030
*** Add for enclosure gates
 1.600035
6' x 10' single Chain link fence, 6' high Add for gates
Ea
109.00
 1.600040
6' x 12' single
Ea
138.00
 1.600045
6' x 15' single
Ea
180.00
 1.600050
6' x 20' double
Ea
208.00
Subdivision  1.61: Cleanup
 1.610000
*** Cleanup
 1.610005
Typical cost Progressive "broom clean" cleanup, as necessary, per 1,000
SF of floor per month
MSF
6.64
 1.610010
Final, total floor area (no glass cleaning) Progressive "broom clean"
cleanup, as necessary, per 1,000 SF of floor per month
MSF
59.80
 1.610015
*** Glass cleaning
 1.610020
Cleaning glass with sponge and squeegee
MSF
14.00
48.60
 1.610025
With solvent, towel, sponge and squeegee Cleaning glass and window
trim
MSF
17.00
201.00
 1.610030
By scraping and solvent Removing paint and concrete splatter from
windows and trim
MSF
42.00
577.00
 1.610035
*** Cleanup
 1.610040
Mop resilient floor by hand Removing paint and concrete splatter from
windows and trim
MSF
1.60
43.50
Subdivision  1.62: Waste Disposal
 1.620000
*** Dump fees
 1.620005
Dumpster, 3 CY trash bin, emptied weekly Dump fees
Mo
330.00
 1.620010
*** Dumpster
 1.620015
Hauling cost, per load Dump fees Dumpster, 40 CY solid waste bin
(lumber, drywall, roofing)
Ea
230.00
 1.620020
Add to per load charge, per ton Dump fees Dumpster, 40 CY solid waste
bin (lumber, drywall, roofing)
Ton
55.00
 1.620025
*** Low‑boy
 1.620030
Hauling cost, per load (use 7 CY as maximum load) Dump fees Low‑boy,
14 CY solid waste container (asphalt, dirt, masonry, concrete)
Ea
230.00
 1.620035
Add to per load charge, per ton Dump fees Low‑boy, 14 CY solid waste
container (asphalt, dirt, masonry, concrete)
Ton
55.00
 1.620040
*** Recycler fees
 1.620045
Greenwaste Recycler fees
Ton
30.00
 1.620050
Asphalt, per load (7 CY) Recycler fees
Ea
100.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  2: Existing Conditions
Subdivision  2.00: Paving and Curb Demolition
 2.000000
*** Bituminous paving demolition
 2.000005
Large area, with a wheel loader Demolish bituminous paving, depths to 3"
(10 SY per CY)
SY
1.56
1.13
 2.000010
Strips 24" wide for utility lines Demolish bituminous paving, depths to 3"
(10 SY per CY)
SY
1.80
1.31
 2.000015
Add for jobs under 50 SY Demolish bituminous paving, depths to 3" (10
SY per CY)
SY
0.41
0.30
 2.000020
to 12" width (65 LF per CY) Demolish bituminous curbs,
LF
1.15
0.83
 2.000025
*** Concrete sidewalk and paving demolition
 2.000030
per 75 SF demolished) Demolish concrete sidewalk or paving 4" concrete
with no reinforcing (1 CY of waste
SF
1.84
1.13
 2.000035
per 65 SF demolished) Demolish concrete sidewalk or paving 4" concrete
with mesh but no rebars (1 CY of waste
SF
2.05
1.48
 2.000040
per 55 SF demolished) Demolish concrete sidewalk or paving 4" concrete
with rebars (1 CY of waste
SF
2.37
1.71
 2.000045
per 55 SF demolished) Demolish concrete sidewalk or paving 5" concrete
with mesh but no rebars (1 CY of waste
SF
2.58
1.86
 2.000050
per 46 SF demolished) Demolish concrete sidewalk or paving 5" concrete
with rebars (1 CY of waste
SF
2.99
2.16
Subdivision  2.01: Fencing demolition
 2.010000
*** Remove chain link fence
 2.010005
To 4' high Remove chain link fence,
LF
1.11
0.37
 2.010010
5 to 8 high Remove chain link fence,
LF
2.04
0.68
 2.010015
To 8' high Remove and salvage chain link fence,
LF
2.71
0.90
 2.010020
*** Remove wood fence
 2.010025
Picket or board fence to 4' high Remove and dispose wood fence
LF
2.08
0.69
 2.010030
Picket or board fence 5 to 8' high Remove and dispose wood fence
LF
2.97
0.99
 2.010035
Split rail fence, 2 or 3 rail Remove and dispose wood fence
LF
1.30
0.43
 2.010040
To 8' high, including one gate post Remove and dispose wood or chain
link fence gate
LF
12.40
4.10
Subdivision  2.02: Highway type guardrail demolition
 2.020000
*** Highway type guardrail demolition
 2.020005
Remove and dispose guardrail Highway type guardrail demolition
LF
1.59
1.27
 2.020010
Remove guardrail in salvage condition Highway type guardrail demolition
LF
2.74
2.19
 2.020015
Remove and dispose guardrail posts Highway type guardrail demolition
Ea
10.00
7.24
Subdivision  2.03: Manhole, Piping and Underground Tank
 2.030000
*** Manhole and catch basin demolition
 2.030005
Brick Manholes and catch basins, demolition, to 10' deep. Break below
collar and plug
Ea
211.00
153.00
 2.030010
Masonry Manholes and catch basins, demolition, to 10' deep. Break below
collar and plug
Ea
218.00
158.00
 2.030015
Precast concrete Manholes and catch basins, demolition, to 10' deep.
Break below collar and plug
Ea
272.00
196.00
 2.030020
Add for sand fill, any of above Manholes and catch basins, demolition, to
10' deep. Break below collar and plug
CY
18.60
5.12
3.70
 2.030025
*** Manhole frame demolition
 2.030030
Remove in salvage condition Frame and cover from manhole or catch
basin
Ea
59.30
42.90
 2.030035
Remove and reset Frame and cover from manhole or catch basin
Ea
163.00
118.00
 2.030040
*** Fire hydrant demolition
 2.030045
Remove and dispose Fire hydrant demolition
Ea
228.00
165.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  2: Existing Conditions
Subdivision  2.03: Manhole, Piping and Underground Tank
 2.030050
*** Break out storm or sewer pipe
Subdivision  2.04: Miscellaneous Sitework Demolition
 2.040000
*** Railroad demolition
 2.040005
Remove track and ties for scrap Railroad demolition, siding quantities
LF
20.20
11.26
 2.040010
Remove and dispose of ballast stone Railroad demolition, siding
quantities
CY
4.41
2.46
 2.040015
Remove wood ties alone Railroad demolition, siding quantities
Ea
5.69
3.17
 2.040020
*** Remove light standards, flagpoles, playground poles
 2.040025
Remove item, in salvage condition
Ea
231.00
109.00
 2.040030
Remove item, no salvage
Ea
27.70
13.00
 2.040035
*** Torch cutting steel plate
 2.040040
To 3/8" thick Torch cutting steel plate
LF
2.65
0.55
Subdivision  2.05: Light wood‑frame structures
 2.050000
*** Light wood‑frame structures
 2.050005
First story (8 SF per CY) Light wood‑frame structures
SF
1.51
0.70
 2.050010
Second story (8 SF per CY) Light wood‑frame structures
SF
2.11
0.97
 2.050015
Third story (8 SF per CY) Light wood‑frame structures
SF
2.78
1.28
Subdivision  2.06: Building demolition with pneumatic tools
 2.060000
*** Building demolition with pneumatic tools
 2.060005
Concrete building (30 SF per CY) Building demolition with pneumatic tools
SF
3.48
1.51
 2.060010
(20 SF per CY) Building demolition with pneumatic tools Reinforced
concrete building
SF
3.95
1.71
 2.060015
Masonry building (50 SF per CY) Building demolition with pneumatic tools
Reinforced concrete building
SF
2.89
1.25
Subdivision  2.07: Building demolition with crane and
 2.070000
*** Building demolition with crane and headache ball
 2.070005
Concrete building (30 SF per CY) Building demolition with crane and
headache ball
SF
1.26
1.05
 2.070010
(20 SF per CY) Building demolition with crane and headache ball
Reinforced concrete building
SF
1.50
1.25
 2.070015
Masonry building (50 SF per CY) Building demolition with crane and
headache ball Reinforced concrete building
SF
1.06
0.88
Subdivision  2.08: Concrete foundation and footing
 2.080000
*** Concrete foundation and footing demolition
 2.080005
(.75 CY per loose CY) Concrete foundation and footing demolition
Non‑reinforced concrete
CY
45.00
45.60
 2.080010
(.60 CY loose per CY) Concrete foundation and footing demolition
Reinforced concrete
CY
64.70
65.50
 2.080015
No dozer used, (.8 CF per loose CF) Chip out concrete using paving
breaker
CF
7.36
3.54
Subdivision  2.09: Gutting a building
 2.090000
*** Gutting a building
 2.090005
Residential buildings (125 SF per CY) Gutting a building
SF
4.08
4.62
 2.090010
Commercial buildings (140 SF per CY) Gutting a building
SF
3.71
4.24
Subdivision  2.10: Partition wall demolition
 2.100000
*** Brick or block partition demolition
 2.100005
4" thick partition (60 SF per CY) Partition wall demolition Brick or block
partition demolition
SF
1.45
0.76
 2.100010
8" thick partition (30 SF per CY) Partition wall demolition Brick or block
partition demolition
SF
2.07
1.08
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  2: Existing Conditions
Subdivision  2.10: Partition wall demolition
 2.100015
12" thick partition (20 SF per CY) Partition wall demolition Brick or block
partition demolition
SF
2.65
1.39
 2.100020
*** Concrete partition wall demolition
 2.100025
Non‑reinforced (18 CF per CY) Partition wall demolition Concrete partition
demolition
CF
9.90
5.18
 2.100030
Reinforced (20 CF per CY) Partition wall demolition Concrete partition
demolition
CF
13.20
6.89
 2.100035
*** Knock down and pile on site
 2.100040
Gypsum or terra cotta on metal lath Partition wall demolition Knock down
with hand tools and pile adjacent to site but no removal. Stud partition
demo
SF
0.98
 2.100045
Drywall on metal or wood studs Partition wall demolition Knock down with
hand tools and pile adjacent to site but no removal. Stud partition
demolitio
SF
1.02
 2.100050
Plaster on metal studs Partition wall demolition Knock down with hand
tools and pile adjacent to site but no removal. Stud partition demolition
(typic
SF
0.94
Subdivision  2.11: Ceiling demolition
 2.110000
*** Ceiling demolition, plaster
 2.110005
Including lath and furring Ceiling demolition Plaster ceiling (typically 175 to
200 SF per CY)
SF
0.91
 2.110010
Including suspended grid Ceiling demolition Plaster ceiling (typically 175
to 200 SF per CY)
SF
0.73
 2.110015
*** Ceiling demolition, acoustic tile
 2.110020
Including suspended grid Ceiling demolition Acoustic tile ceiling (typically
200 to 250 SF per CY)
SF
0.36
 2.110025
Including grid in salvage condition Ceiling demolition Acoustic tile ceiling
(typically 200 to 250 SF per CY)
SF
0.69
 2.110030
Including strip furring Ceiling demolition Acoustic tile ceiling (typically 200
to 250 SF per CY)
SF
0.51
 2.110035
Tile glued to ceiling Ceiling demolition Acoustic tile ceiling (typically 200 to
250 SF per CY)
SF
0.54
 2.110040
*** Ceiling demolition, drywall
 2.110045
to joists Ceiling demolition Drywall ceiling (typically 250 to 300 SF per CY)
Nailed or attached with screws
SF
0.44
 2.110050
Including strip furring Ceiling demolition Drywall ceiling (typically 250 to
300 SF per CY) Nailed or attached with screws
SF
0.83
Subdivision  2.12: Roof demolition
 2.120000
*** Roof demolition
 2.120005
Asphalt shingles (2.50 Sq per CY) Roof surface removal, using hand tools
Sq
30.80
 2.120010
(1.25 Sq per CY) Roof surface removal, using hand tools Built‑up roofing,
including sheathing and gravel
Sq
106.00
 2.120015
(.70 Sq per CY) Roof surface removal, using hand tools Clay or concrete
tile
Sq
37.30
 2.120020
(.80 Sq per CY) Concrete plank, no covering
Sq
39.90
 2.120025
(.70 Sq per CY) Gypsum plank, no covering
Sq
29.70
 2.120030
(.50 Sq per CY) Metal deck, no covering
Sq
82.30
 2.120035
(1.66 Sq per CY) Wood shingles
Sq
27.40
 2.120040
Remove gravel stop Wood shingles
LF
2.54
Subdivision  2.13: Floor slab demolition
 2.130000
*** Slab on grade demolition, 4" to 6" thick
 2.130005
With wire mesh (55 SF per CY) Floor slab demolition Slab on grade, 4" to
6" thick, reinforced
SF
2.07
1.84
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  2: Existing Conditions
Subdivision  2.13: Floor slab demolition
 2.130010
With number 4 bars (45 SF per CY) Floor slab demolition Slab on grade,
4" to 6" thick, reinforced
SF
2.28
1.20
 2.130015
(35 SF per CY) Floor slab demolition Slab, suspended, 6" to 8" thick, free
fall
SF
3.34
1.75
 2.130020
*** Slab fill demolition
 2.130025
On metal deck (45 SF per CY) Floor slab demolition Slab fill, lightweight
concrete fill
SF
1.05
0.55
 2.130030
Topping, insulating (150 SF per CY) Floor slab demolition Slab fill,
lightweight concrete fill
SF
0.83
0.44
Subdivision  2.14: Floor covering demolition
 2.140000
*** Floor covering demolition
 2.140005
(200 SF per CY) Floor covering demolition Ceramic or quarry tile, brick
SF
1.05
 2.140010
(270 SF per CY) Floor covering demolition Resilient materials only
SF
0.65
 2.140015
(225 SF per CY) Floor covering demolition Terrazzo tile
SF
1.16
 2.140020
(200 SF per CY) Floor covering demolition Wood block floor, laid in mastic
SF
1.85
 2.140025
(225 SF per CY) Floor covering demolition Wood, residential strip floor
SF
1.16
Subdivision  2.15: Cutting openings in frame walls
 2.150000
*** Cutting openings in frame walls
 2.150005
Metal stud wall with stucco or plaster Cutting openings in frame walls
SF
3.41
 2.150010
Wood stud wall with drywall Cutting openings in frame walls
SF
1.85
 2.150015
Dust control partitions, 6 mil plastic Cutting openings in frame walls
SF
0.30
0.45
Subdivision  2.16: Debris removal
 2.160000
*** Debris removal
 2.160005
to trash chute and dump Debris removal Wheelbarrow, 50'
CF
0.65
 2.160010
to trash chute and dump Debris removal Wheelbarrow, 100'
CF
0.80
 2.160015
to trash chute and dump Debris removal Wheelbarrow, 50' to elevator,
descend 10 floors
CF
0.87
 2.160020
*** Trash chutes
 2.160025
18" diameter Debris removal Trash chutes One‑time charge for up to
six‑months usage. Use 50 LF as minimum charge
LS
1,160.00
 2.160030
36" diameter Debris removal Trash chutes One‑time charge for up to
six‑months usage. Use 50 LF as minimum charge
LS
1,735.00
Subdivision  2.17: Load demolition debris on a truck
 2.170000
*** Load demolition debris on a truck
 2.170005
Truck loaded by hand Load demolition debris on a truck
CY
30.70
10.20
 2.170010
Truck loaded using a wheel loader Load demolition debris on a truck
CY
14.60
6.73
Subdivision  2.18: Removal of interior items
 2.180000
*** Removal of hollow metal door and frame
 2.180005
Single door to 4' x 7' Removal of interior items Hollow metal door and
frame in a masonry wall. (2 doors per CY)
Ea
36.30
 2.180010
Two doors, per opening to 8' x 7' Removal of interior items Hollow metal
door and frame in a masonry wall. (2 doors per CY)
Ea
54.40
 2.180015
*** Removal of wood door and frame
 2.180020
Single door to 4' x 7' Removal of interior items Wood door and frame in a
wood‑frame wall (2 doors per CY)
Ea
18.10
 2.180025
Two doors, per opening to 8' x 7' Removal of interior items Wood door and
frame in a wood‑frame wall (2 doors per CY)
Ea
27.20
 2.180030
*** Remove door and frame from masonry wall in salvage condition
 2.180035
Hollow metal door to 4' x 7' Removal of interior items Remove door and
frame in masonry wall, salvage condition
Ea
81.30
 2.180040
Ea
40.60
Wood door to 4' x 7' Removal of interior items Remove door and frame in
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
masonry wall, salvage condition
 2.180045
*** Removal of interior items
 2.180050
Per SF of mat area Removal of interior items Frame for resilient mat,
metal
SF
2.19
Subdivision  2.19: Structure Moving
 2.190000
*** Concrete or masonry structure moving
 2.190005
1,000 to 2,000 SF Structure Moving Concrete or masonry structures, 12"
maximum thick walls or floors
SF
6.18
7.99
 2.190010
2,000 to 4,000 SF Structure Moving Concrete or masonry structures, 12"
maximum thick walls or floors
SF
5.48
7.08
 2.190015
*** Wood frame structure moving
 2.190020
1,000 to 2,000 SF Structure Moving Wood frame
SF
5.22
6.75
 2.190025
2,000 to 4,000 SF Structure Moving Wood frame
SF
4.82
6.23
 2.190030
*** Steel frame structure moving
 2.190035
1,000 to 2,000 SF Structure Moving Steel frame
SF
7.90
10.22
 2.190040
2,000 to 4,000 SF Structure Moving Steel frame
SF
7.32
9.46
Subdivision  2.20: Asbestos Hazard Surveys
 2.200000
*** Asbestos Hazard Surveys
 2.200005
4 hour minimum Asbestos Hazard Surveys Asbestos hazard survey and
sample collection (10,000 SF per hour)
Hour
80.00
 2.200010
10 sample minimum Asbestos Hazard Surveys Sample analysis (usually
one sample per 1,000 SF)
Ea
48.00
 2.200015
$200 minimum Asbestos Hazard Surveys Report writing (per 1,000 SF of
floor)
MSF
25.00
Subdivision  2.21: Asbestos Removal, Subcontract
 2.210000
*** Asbestos removal, ceiling insulation in containment structure
 2.210005
500 to 5,000 SF job Asbestos Removal, Subcontract Ceiling insulation in
containment structure
SF
37.00
 2.210010
5,000 to 20,000 SF job Asbestos Removal, Subcontract Ceiling insulation
in containment structure
SF
25.00
 2.210015
*** Asbestos removal, pipe insulation in containment structure
 2.210020
100 to 1,000 LF of 6" pipe Asbestos Removal, Subcontract Pipe insulation
in containment structure
LF
65.00
 2.210025
1,000 to 3,000 LF of 6" pipe Asbestos Removal, Subcontract Pipe
insulation in containment structure
LF
42.00
 2.210030
*** Asbestos removal, pipe insulation in glove bags
 2.210035
100 to 1,000 LF of 6" pipe Asbestos Removal, Subcontract Pipe insulation
using glove bags
LF
55.00
 2.210040
1,000 to 3,000 LF of 6" pipe Asbestos Removal, Subcontract Pipe
insulation using glove bags
LF
42.00
Subdivision  2.22: Excavation for Concrete Work
 2.220000
*** Excavation for Concrete Work
 2.220005
per corner Batterboards, lay out for footings,
Ea
7.00
50.40
 2.220010
*** Trenching with a 1/2 CY utility backhoe
 2.220015
.111 CY per LF (135 LF/Hr) 18" x 24" depth,
LF
0.63
0.27
 2.220020
.222 CY per LF (68 LF/Hr) 24" x 36" depth,
LF
1.22
0.53
 2.220025
.444 CY per LF (34 LF/Hr) 36" x 48" depth,
LF
2.48
1.07
 2.220030
.741 CY per LF (20 LF/Hr) 48" x 60" depth,
LF
4.16
1.80
 2.220035
15 CY per hour Per cubic yard,
CY
5.59
2.42
 2.220040
*** Hand excavation for concrete work
 2.220045
of obstructions Hand labor Clearing trench shoulders
LF
0.62
 2.220050
Breaking and stacking Hand labor Hard pan or rock outcropping
CY
117.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  3: Concrete
Subdivision  3.00: Concrete
 3.000000
*** Capillary fill under slabs
 3.000005
small job Capillary fill, one CY covers 81 SF at 4" deep 4", hand graded
and rolled,
SF
0.31
0.51
 3.000010
larger job Capillary fill, one CY covers 81 SF at 4" deep 4", machine
graded and rolled,
SF
0.31
0.25
0.14
 3.000015
Add for each extra 1" hand graded Capillary fill, one CY covers 81 SF at
4" deep 4", machine graded and rolled,
SF
0.09
0.15
 3.000020
Add for each extra 1" machine graded Capillary fill, one CY covers 81 SF
at 4" deep 4", machine graded and rolled,
SF
0.09
0.04
0.03
 3.000025
*** Sand fill under slabs
 3.000030
2" sand cushion, hand spread, 1 throw Sand fill, 1 CY covers 162 SF at 2"
deep
SF
0.13
0.11
 3.000035
Add for each additional 1 Sand fill, 1 CY covers 162 SF at 2" deep
SF
0.06
0.07
 3.000040
*** Waterproof membrane under slabs
 3.000045
.004" (4 mil) clear or black Waterproof membrane, polyethylene, over
sand bed, including 20% lap and waste
SF
0.06
0.04
 3.000050
.006" (6 mil) clear or black Waterproof membrane, polyethylene, over
sand bed, including 20% lap and waste
SF
0.07
0.04
Subdivision  3.01: Wall footing, grade beam or tie beam
 3.010000
*** Wall footing, grade beam or tie beam forms
 3.010005
1 use Wall footing, grade beam or tie beam forms
SFCA
1.83
2.91
 3.010010
3 uses Wall footing, grade beam or tie beam forms
SFCA
1.04
2.08
 3.010015
5 uses Wall footing, grade beam or tie beam forms
SFCA
0.88
1.66
 3.010020
Add for stepped footings Wall footing, grade beam or tie beam forms
SFCA
0.51
1.16
 3.010025
Add for keyed joint, 1 use Wall footing, grade beam or tie beam forms
LF
0.76
0.83
 3.010030
*** Reinforcing bar supports for footing, grade beam and tie beam forms
 3.010035
1 use
LF
0.79
2.49
 3.010040
3 uses
LF
0.52
2.08
 3.010045
5 uses
LF
0.47
1.66
 3.010050
*** Integral starter wall forms
Subdivision  3.02: Column footing or pile cap forms
 3.020000
*** Column footing or pile cap forms
 3.020005
1 use Square or rectangular column forms
SFCA
2.46
3.74
 3.020010
3 uses Square or rectangular column forms
SFCA
1.36
2.91
 3.020015
5 uses Square or rectangular column forms
SFCA
1.13
2.49
 3.020020
*** Octagonal, hexagonal or triangular forms
 3.020025
1 use Octagonal, hexagonal or triangular forms
SFCA
2.46
4.86
 3.020030
3 uses Octagonal, hexagonal or triangular forms
SFCA
1.36
3.78
 3.020035
5 uses Octagonal, hexagonal or triangular forms
SFCA
1.13
3.24
 3.020040
*** Reinforcing bar supports for column forms
 3.020045
1 use Reinforcing bar supports for column forms
LF
0.54
2.49
 3.020050
*** Anchor bolt templates
Subdivision  3.03: Slab‑on‑grade forms
 3.030000
*** Slab on grade edge forms to 6" high
 3.030005
1 use Edge forms to 6" high, 1.5 BF per LF of form (.5 SFCA per LF)
LF
1.20
2.70
 3.030010
3 uses Edge forms to 6" high, 1.5 BF per LF of form (.5 SFCA per LF)
LF
0.72
2.53
 3.030015
5 uses Edge forms to 6" high, 1.5 BF per LF of form (.5 SFCA per LF)
LF
0.63
2.28
 3.030020
*** Slab on grade edge forms over 6" high to 12" high
 3.030025
1 use
LF
1.67
3.74
 3.030030
3 uses
LF
0.96
3.57
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  3: Concrete
Subdivision  3.03: Slab‑on‑grade forms
 3.030035
5 uses
LF
0.82
3.32
 3.030040
*** Slab on grade edge forms over 12" high to 24" high
 3.030045
1 use
LF
3.09
5.15
 3.030050
3 uses
LF
1.67
4.94
Subdivision  3.04: Wall forms
 3.040000
*** Wall form heights to 4
 3.040005
1 use
SFCA
2.75
4.94
 3.040010
3 uses
SFCA
1.50
3.32
 3.040015
5 uses
SFCA
1.25
2.86
 3.040020
Add for 1 side battered
SFCA
0.27
0.66
 3.040025
Add for 2 sides battered
SFCA
0.55
1.00
 3.040030
*** Wall form heights over 4 to 6
 3.040035
1 use
SFCA
3.06
5.81
 3.040040
3 uses
SFCA
1.66
4.15
 3.040045
5 uses
SFCA
1.38
3.32
 3.040050
Add for 1 side battered
SFCA
0.31
0.66
Subdivision  3.05: Column forms for square or rectangular
 3.050000
*** Up to 12" x 12 column forms
 3.050005
1 use
SFCA
3.13
5.40
 3.050010
3 uses
SFCA
1.69
3.74
 3.050015
5 uses
SFCA
1.40
3.32
 3.050020
*** Over 12" x 12" to 16" x 16" column forms
 3.050025
1 use
SFCA
3.16
4.15
 3.050030
3 uses
SFCA
1.71
2.86
 3.050035
5 uses
SFCA
1.41
2.53
 3.050040
*** Over 16" x 16" to 20" x 20" column forms
 3.050045
1 use
SFCA
3.19
3.32
 3.050050
3 uses
SFCA
1.72
2.53
Subdivision  3.06: Column capitals for square columns
 3.060000
*** Up to 12" x 12" column capital form
 3.060005
1 use of forms Up to 12" x 12" column, 6.0 SFCA
Ea
21.80
166.00
 3.060010
3 uses of forms Up to 12" x 12" column, 6.0 SFCA
Ea
10.90
125.00
 3.060015
*** Over 12" x 12" to 16" x 16" column capital form
 3.060020
1 use of forms Over 12" x 12" to 16" x 16" column, 10.7 SFCA
Ea
38.80
249.00
 3.060025
3 uses of forms Over 12" x 12" to 16" x 16" column, 10.7 SFCA
Ea
19.40
166.00
 3.060030
*** Over 16" x 16" to 20" x 20" column capital form
 3.060035
1 use of forms Over 16" x 16" to 20" x 20" column, 16.6 SFCA
Ea
60.20
345.00
 3.060040
3 uses of forms Over 16" x 16" to 20" x 20" column, 16.6 SFCA
Ea
30.10
249.00
 3.060045
*** Over 20" x 20" to 24" x 24" column capital form
 3.060050
1 use of forms Over 20" x 20" to 24" x 24" column, 24.0 SFCA
Ea
87.10
498.00
Subdivision  3.07: Column forms for round columns
 3.070000
*** Column forms for round columns
 3.070005
Bracing per LF (add to each cost below) Column forms for round columns
LF
0.42
 3.070010
8" spiral type Column forms for round columns
LF
1.58
6.89
 3.070015
10" spiral type Column forms for round columns
LF
1.98
7.55
 3.070020
12" spiral type Column forms for round columns
LF
2.46
8.59
 3.070025
14" spiral type Column forms for round columns
LF
2.97
9.30
 3.070030
16" spiral type Column forms for round columns
LF
3.37
9.63
 3.070035
20" spiral type Column forms for round columns
LF
5.14
10.40
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  3: Concrete
Subdivision  3.07: Column forms for round columns
 3.070040
24" spiral type Column forms for round columns
LF
6.49
11.40
 3.070045
30" spiral type Column forms for round columns
LF
10.00
12.00
 3.070050
36" spiral type Column forms for round columns
LF
12.00
12.80
Subdivision  3.08: Column capitals for round columns
 3.080000
*** Column capitals for round columns
 3.080005
3'6" (100 pounds) 1 use
Ea
193.00
166.00
 3.080010
3'6" (100 pounds) 3 uses
Ea
64.60
166.00
 3.080015
4'0" (125 pounds) 1 use
Ea
208.00
166.00
 3.080020
4'0" (125 pounds) 3 uses
Ea
69.50
166.00
 3.080025
4'6" (150 pounds) 1 use
Ea
216.00
178.00
 3.080030
4'6" (150 pounds) 3 uses
Ea
72.10
178.00
 3.080035
5'0" (175 pounds) 1 use
Ea
227.00
187.00
 3.080040
5'0" (175 pounds) 3 uses
Ea
81.00
187.00
 3.080045
5'6" (200 pounds) 1 use
Ea
261.00
187.00
 3.080050
5'6" (200 pounds) 3 uses
Ea
87.40
187.00
Subdivision  3.09: Beam and girder forms
 3.090000
*** Beam and girder forms
 3.090005
1 use Beam and girder forms
SFCA
3.41
6.18
 3.090010
3 uses Beam and girder forms
SFCA
1.83
5.85
 3.090015
5 uses Beam and girder forms
SFCA
1.51
4.98
Subdivision  3.10: Shores for beams and girders
 3.100000
*** Shores for beams and girders
 3.100005
1 use Shores for beams and girders
Ea
28.40
62.30
 3.100010
3 uses Shores for beams and girders
Ea
15.70
41.50
 3.100015
5 uses Shores for beams and girders
Ea
13.20
31.00
Subdivision  3.11: Waffle slab‑joist pans, monolithic
 3.110000
*** Waffle slab‑joist pans, monolithic
 3.110005
1 use Waffle slab‑joist pans, monolithic Metal pans, 10,000 to 20,000 SF
SF
4.89
4.15
 3.110010
2 uses Waffle slab‑joist pans, monolithic Metal pans, 10,000 to 20,000 SF
SF
2.74
2.74
 3.110015
*** Fiberglass pans for monolithic waffle slab‑joists
 3.110020
1 use Waffle slab‑joist pans, monolithic Fiberglass pans, 10,000 to 20,000
SF
SF
4.99
3.20
 3.110025
2 uses Waffle slab‑joist pans, monolithic Fiberglass pans, 10,000 to
20,000 SF
SF
2.86
2.53
Subdivision  3.12: Flat slab with beams, monolithic
 3.120000
*** Flat slab with beams, monolithic
 3.120005
One‑way beam 1 use Flat slab with beams, monolithic
SFCA
3.96
4.57
 3.120010
One‑way beam 2 uses Flat slab with beams, monolithic
SFCA
3.05
3.32
 3.120015
Two‑way beam 1 use Flat slab with beams, monolithic
SFCA
5.45
6.31
 3.120020
Two‑way beam 2 uses Flat slab with beams, monolithic
SFCA
3.21
4.15
Subdivision  3.13: Structural flat slab
 3.130000
*** Structural flat slab
 3.130005
Edge forms Structural flat slab
LF
1.67
2.99
 3.130010
Slab forms 1 use Structural flat slab
SFCA
3.36
2.86
 3.130015
Slab forms 3 uses Structural flat slab
SFCA
1.81
1.99
 3.130020
Slab forms 5 uses Structural flat slab
SFCA
1.49
1.78
Subdivision  3.14: Additional forming costs for elevated
 3.140000
*** Additional forming costs for elevated slabs, if required
 3.140005
Control joints Additional forming costs for elevated slabs, if required
LF
1.79
1.29
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  3: Concrete
Subdivision  3.14: Additional forming costs for elevated
 3.140010
Curbs & pads Additional forming costs for elevated slabs, if required
SFCA
3.36
3.44
 3.140015
Depressions Additional forming costs for elevated slabs, if required
SFCA
1.01
3.44
 3.140020
Keyed joints Additional forming costs for elevated slabs, if required
LF
0.75
1.29
Subdivision  3.15: Miscellaneous formwork
 3.150000
*** Miscellaneous formwork
 3.150005
Flat soffits & landings Miscellaneous formwork
SFCA
5.21
6.89
 3.150010
Sloping soffits Miscellaneous formwork
SFCA
5.38
6.89
 3.150015
Stair risers (steps) Miscellaneous formwork
SFCA
2.02
4.98
Subdivision  3.16: Grade 60 ASTM A615 Rebars, 20 lengths,
 3.160000
*** Grade 60 ASTM A615 Rebars, 20 lengths,
 3.160005
3/8" x 20 Grade 60 ASTM A615 Rebars, 20 lengths,
Ea
3.60
 3.160010
1/2" x 20 Grade 60 ASTM A615 Rebars, 20 lengths,
Ea
5.81
 3.160015
5/8" x 20 Grade 60 ASTM A615 Rebars, 20 lengths,
Ea
9.07
 3.160020
3/4" x 20 Grade 60 ASTM A615 Rebars, 20 lengths,
Ea
10.50
 3.160025
1" x 20 Grade 60 ASTM A615 Rebars, 20 lengths,
Ea
24.80
Subdivision  3.17: Reinforcing for Cast‑in‑Place Concrete
 3.170000
*** Reinforcing steel in footings, foundations and grade beams
 3.170005
1/4" diameter, #2 rebar Reinforcing steel placed and tied in footings,
foundations and grade beams
Lb
0.78
0.76
 3.170010
1/4" diameter, #2 rebar (.17 lb per LF) Reinforcing steel placed and tied in
footings, foundations and grade beams
LF
0.14
0.15
 3.170015
3/8" diameter, #3 rebar Reinforcing steel placed and tied in footings,
foundations and grade beams
Lb
0.49
0.56
 3.170020
3/8" diameter, #3 rebar (.38 lb per LF) Reinforcing steel placed and tied in
footings, foundations and grade beams
LF
0.21
0.20
 3.170025
1/2" diameter, #4 rebar Reinforcing steel placed and tied in footings,
foundations and grade beams
Lb
0.47
0.51
 3.170030
1/2" diameter, #4 rebar (.67 lb per LF) Reinforcing steel placed and tied in
footings, foundations and grade beams
LF
0.35
0.35
 3.170035
5/8" diameter, #5 rebar Reinforcing steel placed and tied in footings,
foundations and grade beams
Lb
0.43
0.46
 3.170040
5/8" diameter, #5 rebar (1.04 lb per LF) Reinforcing steel placed and tied
in footings, foundations and grade beams
LF
0.49
0.46
 3.170045
3/4" diameter, #6 rebar Reinforcing steel placed and tied in footings,
foundations and grade beams
Lb
0.41
0.41
 3.170050
3/4" diameter, #6 rebar (1.50 lb per LF) Reinforcing steel placed and tied
in footings, foundations and grade beams
LF
0.67
0.61
Subdivision  3.18: Ready‑Mix Concrete
 3.180000
*** Ready‑Mix Concrete
 3.180005
5.0 sack mix, 2,000 PSI Ready‑Mix Concrete
CY
101.00
 3.180010
6.0 sack mix, 3,000 PSI Ready‑Mix Concrete
CY
105.00
 3.180015
6.6 sack mix, 3,500 PSI Ready‑Mix Concrete
CY
107.00
 3.180020
7.1 sack mix, 4,000 PSI Ready‑Mix Concrete
CY
109.00
 3.180025
8.5 sack mix, 5,000 PSI Ready‑Mix Concrete
CY
125.00
 3.180030
*** Extra costs for ready‑mix concrete
 3.180035
Add for less than 10 CY per load Extra costs for ready‑mix concrete
CY
20.00
 3.180040
Add for delivery over 20 miles Extra costs for ready‑mix concrete
Mile
4.50
 3.180045
per minute of extra time Extra costs for ready‑mix concrete Add for
standby charge in excess of 5 minutes per CY delivered,
Ea
2.25
 3.180050
5 sack mix Extra costs for ready‑mix concrete Add for high early strength
concrete
CY
12.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  3: Concrete
Subdivision  3.19: Concrete Pumping, Subcontract
 3.190000
*** Concrete pumping, 3/8" aggregate mix
 3.190005
Cost per cubic yard (pumping only) 3/8" aggregate mix (pea gravel), using
hose to 200'
CY
12.00
 3.190010
Add for hose over 200', per LF 3/8" aggregate mix (pea gravel), using
hose to 200'
LF
1.50
 3.190015
*** Concrete pumping, 3/4" aggregate mix
 3.190020
Cost per cubic yard (pumping only) 3/4" aggregate mix, using hose to 200'
CY
12.50
 3.190025
Add for hose over 200', per LF 3/4" aggregate mix, using hose to 200'
LF
1.50
Subdivision  3.20: Concrete Pumping with a Boom Truck,
 3.200000
*** Concrete Pumping with a Boom Truck, Subcontract
 3.200005
23 meter boom (75'), 70 CY per hour rating Costs include operator and
oiler where necessary
Hr
110.00
 3.200010
Add per CY pumped with 23 meter boom Costs include operator and oiler
where necessary
CY
2.50
 3.200015
28 meter boom (92'), 70 CY per hour rating Costs include operator and
oiler where necessary
Hr
125.00
 3.200020
Add per CY pumped with 28 meter boom Costs include operator and oiler
where necessary
CY
2.50
 3.200025
32 meter boom (105'), 90 CY per hour rating Costs include operator and
oiler where necessary
Hr
145.00
 3.200030
Add per CY pumped with 32 meter boom Costs include operator and oiler
where necessary
CY
2.50
 3.200035
36 meter boom (120'), 90 CY per hour rating Costs include operator and
oiler where necessary
Hr
180.00
 3.200040
Add per CY pumped with 36 meter boom Costs include operator and oiler
where necessary
CY
2.50
 3.200045
42 meter boom (138'), 100 CY per hour rating Costs include operator and
oiler where necessary
Hr
240.00
 3.200050
Add per CY pumped with 42 meter boom Costs include operator and oiler
where necessary
CY
3.00
Subdivision  3.21: Ready‑Mix Concrete and Placing
 3.210000
*** Ready‑Mix Concrete and Placing
 3.210005
By crane (60 ton crawler crane) Columns
CY
105.00
35.00
13.60
 3.210010
and operator) Columns By pump (28 meter boom truck
CY
116.00
2.43
5.27
 3.210015
*** Placing ready‑mix concrete in slabs on grade
 3.210020
Direct from chute Slabs‑on‑grade
CY
105.00
15.60
 3.210025
By crane (60 ton crawler crane) Slabs‑on‑grade
CY
105.00
23.80
9.25
 3.210030
20 CY/ hour) Slabs‑on‑grade By pump (trailer mounted,
CY
116.00
7.36
5.43
 3.210035
With buggy Slabs‑on‑grade By pump (trailer mounted,
CY
116.00
19.70
6.77
 3.210040
*** Placing ready‑mix concrete in elevated slabs
 3.210045
By crane (60 ton crawler crane) Elevated slabs
CY
105.00
34.80
13.50
 3.210050
and operator) Elevated slabs By pump (28 meter boom truck
CY
116.00
2.12
4.84
Subdivision  3.22: 4" thick 4' x 6' equipment pad
 3.220000
*** 4" thick 4' x 6' equipment pad
 3.220005
Hand trimming and shaping, 24 SF 4" thick 4' x 6' equipment pad
LS
18.60
 3.220010
20 LF, 5 uses 4" thick 4' x 6' equipment pad Lay out, set and strip edge
forms,
LS
6.00
52.80
 3.220015
mesh, 24 SF 4" thick 4' x 6' equipment pad Place W2.9 x W2.9 x 6" x 6"
LS
12.20
4.91
 3.220020
.3 CY 4" thick 4' x 6' equipment pad Place ready‑mix concrete, from chute
LS
31.50
4.61
 3.220025
Finish concrete, broom finish 4" thick 4' x 6' equipment pad Place
ready‑mix concrete, from chute
LS
25.80
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  3: Concrete
Subdivision  3.22: 4" thick 4' x 6' equipment pad
 3.220030
Cure concrete, curing paper 4" thick 4' x 6' equipment pad Place
ready‑mix concrete, from chute
LS
1.00
4.50
 3.220035
Total job cost for 4" thick 24 SF pad 4" thick 4' x 6' equipment pad Place
ready‑mix concrete, from chute
LS
50.70
111.00
 3.220040
Cost per SF for 4" thick 24 SF pad 4" thick 4' x 6' equipment pad Place
ready‑mix concrete, from chute
SF
2.11
4.63
 3.220045
.3 CY job 4" thick 4' x 6' equipment pad Place ready‑mix concrete, from
chute Cost per CY of 4" thick concrete,
CY
169.00
371.00
Subdivision  3.23: 8" thick 10' x 10' equipment pad
 3.230000
*** 8" thick 10' x 10' equipment pad
 3.230005
Hand trimming and shaping, 100 SF 8" thick 10' x 10' equipment pad
LS
101.00
 3.230010
40 LF, 5 uses 8" thick 10' x 10' equipment pad Lay out, set and strip edge
forms,
LS
19.20
133.00
 3.230015
100 SF 8" thick 10' x 10' equipment pad Place W2.9 x W2.9 x 6" x 6"
mesh,
LS
51.00
20.30
 3.230020
2.5 CY 8" thick 10' x 10' equipment pad Place ready‑mix concrete, from
chute
LS
263.00
39.20
 3.230025
Finish concrete, broom finish 8" thick 10' x 10' equipment pad Place
ready‑mix concrete, from chute
LS
92.00
 3.230030
Cure concrete, curing paper 8" thick 10' x 10' equipment pad Place
ready‑mix concrete, from chute
LS
4.00
18.70
 3.230035
Total job cost for 8" thick 100 SF pad 8" thick 10' x 10' equipment pad
Place ready‑mix concrete, from chute
LS
337.20
404.00
 3.230040
Cost per SF for 8" thick 100 SF job 8" thick 10' x 10' equipment pad Place
ready‑mix concrete, from chute
SF
3.37
4.04
 3.230045
2.5 CY job 8" thick 10' x 10' equipment pad Place ready‑mix concrete,
from chute Cost per CY of 8" thick concrete,
CY
135.00
161.68
Subdivision  3.24: Note
 3.240000
*** Note
 3.240005
less than 10 delivered Note Add for each CY
CY
20.00
Subdivision  3.25: Floor Slab Assemblies
 3.250000
*** Floor Slab Assemblies
 3.250005
3,000 PSI concrete Based on 100' x 75' slab (7,500 SF)
CY
118.00
 3.250010
4" thick slab Based on 100' x 75' slab (7,500 SF)
SF
2.61
1.05
0.11
0.02
 3.250015
5" thick slab Based on 100' x 75' slab (7,500 SF)
SF
2.94
1.09
0.12
0.35
 3.250020
6" thick slab Based on 100' x 75' slab (7,500 SF)
SF
3.27
1.14
0.13
0.68
Subdivision  3.26: 4" thick 100' x 75' slab
 3.260000
*** 4" thick 100' x 75' slab
 3.260005
(no import or export) 4" thick 100' x 75' slab Grade sandy loam site using
a D‑4 tractor, 140 CY, balanced job,
LS
112.00
65.80
 3.260010
140 CY 4" thick 100' x 75' slab Buy and spread 6" crushed rock base
using a D‑4 tractor,
LS
3,860.00
664.00
391.00
 3.260015
350 LF, 5 uses 4" thick 100' x 75' slab Lay out, set and strip edge forms,
LS
105.00
796.00
 3.260020
7,500 SF 4" thick 100' x 75' slab Place .006" polyethylene vapor barrier
LS
516.00
321.00
 3.260025
7,500 SF 4" thick 100' x 75' slab Place W2.9 x W2.9 x 6" x 6" mesh,
LS
4,800.00
1,520.00
 3.260030
200 LF, 1 use 4" thick 100' x 75' slab Place and remove 2" x 4" keyway,
LS
86.00
358.00
 3.260035
Place 4" concrete, 93 CY, from chute 4" thick 100' x 75' slab Place and
remove 2" x 4" keyway,
LS
9,770.00
1,450.00
 3.260040
Float finish 7,500 SF 4" thick 100' x 75' slab Place and remove 2" x 4"
keyway,
LS
2,280.00
416.00
 3.260045
Cure with slab curing paper 4" thick 100' x 75' slab Place and remove 2" x
4" keyway,
LS
450.00
243.00
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  3: Concrete
Subdivision  3.26: 4" thick 100' x 75' slab
 3.260050
100' x 75' floor slab 4" thick 100' x 75' slab Total job cost 4" thick
LS
19,587.00
7,740.00
872.80
Subdivision  3.27: Cast‑in‑Place Concrete, Subcontract
 3.270000
*** Concrete foundations
 3.270005
Institutional or office buildings Foundations
CY
494.00
 3.270010
Heavy engineered structures Foundations
CY
537.00
 3.270015
*** Structural concrete walls
 3.270020
Single story, 8" wall Structural concrete walls
CY
667.00
 3.270025
Single story, 10" wall Structural concrete walls
CY
735.00
 3.270030
Multi‑story, 8" wall Structural concrete walls
CY
857.00
 3.270035
Multi‑story, 10 Structural concrete walls
CY
898.00
 3.270040
Slip formed 8" wall Structural concrete walls
CY
756.00
 3.270045
*** Structural concrete slabs
 3.270050
100 pounds reinforcing Structural slabs, including shoring, 6", 1 way
beams,
CY
785.00
Subdivision  3.28: Cast‑in‑Place Concrete Steps on Grade
 3.280000
*** Fabricate and erect concrete step forms
 3.280005
Side forms, 1.7 BF per LF of tread
LF
0.71
3.33
 3.280010
Riser forms, 1.5 BF per LF of tread
LF
0.62
1.66
 3.280015
Rebar, #3, Grade 60, 1 pound per LF of tread
LF
0.47
0.37
 3.280020
*** Embedded steel step nosing
 3.280025
Angle iron, 4.5 pounds per LF of tread. Embedded steel step nosing,
2‑1/2" x 2‑1/2" x 1/4" black mild steel
LF
3.74
0.17
 3.280030
Concrete, .03 CY per LF of tread Embedded steel step nosing, 2‑1/2" x
2‑1/2" x 1/4" black mild steel
LF
3.15
1.25
 3.280035
Total cost per LF of risers Embedded steel step nosing, 2‑1/2" x 2‑1/2" x
1/4" black mild steel
LF
8.69
6.78
 3.280040
Total cost per CY of concrete Embedded steel step nosing, 2‑1/2" x 2‑1/2"
x 1/4" black mild steel
CY
289.66
226.00
Subdivision  3.29: Concrete Accessories
 3.290000
*** Concrete Accessories
 3.290005
50 pound bag, granules Bentonite
Ea
34.90
 3.290010
3 gallon Volclay Bentoseal Bentonite
Ea
132.00
 3.290015
4 x 15 Bentonite geotextile roll Bentonite
Ea
71.90
 3.290020
*** Bond breaker and form release
 3.290025
Lumber & plywood form release, 200 SF/gal Bond breaker and form
release, Thompson's CBA, spray on
SF
0.23
0.22
 3.290030
Metal form release, 600 SF per gallon Bond breaker and form release,
Thompson's CBA, spray on
SF
0.08
0.11
 3.290035
Casting bed form breaker, 300 SF per gallon Bond breaker and form
release, Thompson's CBA, spray on
SF
0.16
0.18
 3.290040
Cure coat, 300 SF per gallon Bond breaker and form release, Thompson's
CBA, spray on
SF
0.16
0.18
 3.290045
*** Chamfer strip
 3.290050
3/4" x 3/4" x 1", 10 lengths Chamfer strip
LF
0.16
0.68
Subdivision  3.30: Concrete Slab Finishes
 3.300000
*** Concrete Slab Finishes
 3.300005
Float finish Concrete Slab Finishes
SF
0.39
 3.300010
*** Trowel finishing
 3.300015
Steel, machine work Trowel finishing
SF
0.61
 3.300020
Steel, hand work Trowel finishing
SF
0.74
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
Division  3: Concrete
Subdivision  3.30: Concrete Slab Finishes
 3.300025
*** Concrete slab finishes
 3.300030
Broom finish Trowel finishing
SF
0.52
 3.300035
Scoring concrete surface, hand work Trowel finishing
LF
0.22
 3.300040
no disposal of slurry Exposed aggregate (washed, including finishing),
SF
0.32
0.65
 3.300045
*** Concrete color hardener
 3.300050
Standard colors Color hardener, nonmetallic, trowel application
Lb
0.76
Subdivision  3.31: Concrete Wall Finishes
 3.310000
*** Concrete Wall Finishes
 3.310005
Cut back ties and patch Concrete Wall Finishes
SF
0.13
0.44
 3.310010
Remove fins Concrete Wall Finishes
LF
0.06
0.31
 3.310015
Grind smooth Concrete Wall Finishes
SF
0.10
0.87
 3.310020
Sack, simple Concrete Wall Finishes
SF
0.07
0.52
 3.310025
Bush hammer light, green concrete Concrete Wall Finishes
SF
0.14
0.87
 3.310030
Bush hammer standard, cured concrete Concrete Wall Finishes
SF
0.14
1.26
 3.310035
Bush hammer, heavy, cured concrete Concrete Wall Finishes
SF
0.14
3.36
 3.310040
Needle gun treatment, large areas Concrete Wall Finishes
SF
0.14
2.53
 3.310045
Wire brush, green Concrete Wall Finishes
SF
0.06
0.61
 3.310050
Wash with acid and rinse Concrete Wall Finishes
SF
0.30
0.17
Subdivision  3.32: Miscellaneous Concrete Finishes
 3.320000
*** Miscellaneous Concrete Finishes
 3.320005
1/16" topping Monolithic natural aggregate topping
SF
0.19
0.25
 3.320010
3/16" topping Monolithic natural aggregate topping
SF
0.43
0.75
 3.320015
1/2" topping Monolithic natural aggregate topping
SF
1.13
0.87
 3.320020
*** Integral colors for concrete
 3.320025
Typically 8 pounds per sack of cement Integral colors,
Lb
2.28
 3.320030
Mono rock, 3/8" wear course only, typical cost Integral colors,
SF
1.33
 3.320035
Kalman 3/4", wear course only, typical cost Integral colors,
SF
2.02
 3.320040
Acid etching, 5% muriatic acid, typical cost Integral colors,
SF
0.39
0.21
 3.320045
Felton sand, for use with white cement Integral colors,
CY
42.00
Subdivision  3.33: Specially Placed Concrete
 3.330000
*** Gunite
 3.330005
Flat plane, vertical areas, 1" thick Gunite, no forms and no reinforcing
included
SF
3.81
 3.330010
Curved arch, barrel, per 1" thickness Gunite, no forms and no reinforcing
included
SF
4.75
 3.330015
Pool or retaining walls, per 1" thickness Gunite, no forms and no
reinforcing included
SF
3.66
 3.330020
Add for architectural finish Gunite, no forms and no reinforcing included
SF
1.45
 3.330025
Wire mesh for gunite 2" x 2", W.9 x W.9 Gunite, no forms and no
reinforcing included
SF
2.25
 3.330030
*** Pressure grouting
 3.330035
Pressure grouting, large quantity, 50/50 mix Gunite, no forms and no
reinforcing included
CY
553.00
Subdivision  3.34: Precast wall panels
 3.340000
*** Precast wall panels
 3.340005
4" thick wall panels (52 lbs per SF) Precast wall panels
SF
10.80
 3.340010
5" thick wall panels (65 lbs per SF) Precast wall panels
SF
11.80
 3.340015
6" thick wall panels (78 lbs per SF) Precast wall panels
SF
12.90
 3.340020
8" thick wall panels (105 lbs per SF) Precast wall panels
SF
13.60
 3.340025
SF
4.24
2‑1/2" of cladding and 2" of fiberboard Add for insulated sandwich wall
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other
panels
Subdivision  3.35: Placing precast structural wall panels
 3.350000
*** Placing precast structural wall panels
 3.350005
1 ton panels to 180' reach (23 per day) Placing precast structural wall
panels
Ea
146.00
68.20
 3.350010
1 to  3 tons, to 121' reach (21 per day) Placing precast structural wall
panels
Ea
159.00
74.50
 3.350015
3 to  5 tons, to 89' reach (18 per day) Placing precast structural wall
panels
Ea
185.00
86.50
 3.350020
5 to  7 tons, to 75' reach (17 per day) Placing precast structural wall
panels
Ea
197.00
91.90
 3.350025
7 to  9 tons, to 65' reach (16 per day)
Ea
209.00
97.80
 3.350030
9 to 11 tons, to 55' reach (15 per day)
Ea
224.00
105.00
 3.350035
11 to 13 tons, to 50' reach (14 per day)
Ea
238.00
111.00
 3.350040
13 to 15 tons, to 43' reach (13 per day)
Ea
258.00
120.00
 3.350045
15 to 20 tons, to 36' reach (11 per day)
Ea
304.00
142.00
 3.350050
20 to 25 tons to 31' reach (10 per day)
Ea
335.00
156.00
Subdivision  3.36: Placing precast partition wall panels
 3.360000
*** Placing precast partition wall panels
 3.360005
(23 per day) Placing precast partition wall panels 1 ton panels to 100'
reach
Ea
146.00
42.50
 3.360010
1 to  2 tons, to 82' reach (21 per day) Placing precast partition wall panels
1 ton panels to 100' reach
Ea
159.00
46.40
 3.360015
2 to  3 tons, to 65' reach (18 per day) Placing precast partition wall panels
1 ton panels to 100' reach
Ea
185.00
53.90
 3.360020
3 to  4 tons, to 57' reach (16 per day) Placing precast partition wall panels
1 ton panels to 100' reach
Ea
209.00
60.90
 3.360025
4 to  5 tons, to 50' reach (15 per day) Placing precast partition wall panels
1 ton panels to 100' reach
Ea
224.00
65.20
 3.360030
5 to  6 tons, to 44' reach (14 per day) Placing precast partition wall panels
1 ton panels to 100' reach
Ea
238.00
69.40
 3.360035
6 to  7 tons, to 40' reach (13 per day) Placing precast partition wall panels
1 ton panels to 100' reach
Ea
258.00
75.10
 3.360040
7 to  8 tons, to 36' reach (11 per day) Placing precast partition wall panels
1 ton panels to 100' reach
Ea
304.00
88.50
 3.360045
8 to 10 tons, to 31' reach (10 per day) Placing precast partition wall panels
1 ton panels to 100' reach
Ea
335.00
94.50
 3.360050
10 to 12 tons to 26' reach (9 per day) Placing precast partition wall panels
1 ton panels to 100' reach
Ea
372.00
108.00
Subdivision  3.37: Precast flat floor slab or floor plank
 3.370000
*** Precast flat floor slab or floor plank
 3.370005
4" thick floor panels (52 lbs per SF) Precast flat floor slab or floor plank
SF
9.14
 3.370010
5" thick floor panels (65 lbs per SF) Precast flat floor slab or floor plank
SF
10.90
 3.370015
6" thick floor panels (78 lbs per SF) Precast flat floor slab or floor plank
SF
14.00
 3.370020
8" thick floor panels (105 lbs per SF) Precast flat floor slab or floor plank
SF
14.50
 3.370025
*** Placing precast flat floor slab or floor plank
 3.370030
(23 per day) 2 ton panels to 150' reach
Ea
146.00
55.30
 3.370035
(21 per day) 2 to  3 tons, to 121' reach
Ea
159.00
60.50
 3.370040
(19 per day) 3 to  4 tons, to 105' reach
Ea
176.00
66.80
 3.370045
4 to  5 tons, to 88' reach (18 per day) 3 to  4 tons, to 105' reach
Ea
186.00
70.60
 3.370050
5 to  6 tons, to 82' reach (17 per day) 3 to  4 tons, to 105' reach
Ea
197.00
74.60
Subdivision  3.38: Precast combination beam and slab units
 3.380000
*** Precast combination beam and slab units
 3.380005
CY
727.00
Slabs with no intermediate beam Precast combination beam and slab
Code
Description
NCE Commercial ‑ Price Book Item List
Unit
Unit Raw Cost
Mat.
Labor
Equip
Sub
Other